MRE5003 Industrial Techniques In Maintenance Management Assignment 4

Study Guide 4: Network technique

Objectives of study guide 4

After completing this study guide, you will be able to:

  • understand the Precedence Diagram (Activity-on-Node) for network planning;
  • apply some of the analytical techniques applicable to network diagrams; and
  • appreciate the GERT, another form of network diagram.

Contents of this study guide

  1. CPM/PERT precedence diagram network planning
  2. PERT: Program evaluation and review techniques
  3. Example 4A: PERT application
  4. Example/activity 4B
  5. Activity 4C
  6. Crashing networks – time/cost optimisation
  7. Example 4D
  8. Activity 4E
  9. Activity 4F
  10. GERT: A conditional sequencing/scheduling method

1. CPM/PERT precedence diagram network planning

In network analysis, an alternate representation to the arrow diagram network is the precedence diagram network. This is a type of Activity-on-Node network format (i.e. AON). AON diagrams show the same logic as with the Activity-on-Arrow diagram, but are more flexible in that more situations can be represented, and is more commonly used in most PC-based software.

On a precedence diagram the activities are represented by boxes at the nodes. The lines linking the boxes indicate the relationship between activities.

An AOA network diagram like this in Figure 4.1:

MREGC5003 Industrial Techniques In Maintenance Management img1

Figure 4.1: Sample Activity-on-Arrow Network Diagram

…has the equivalent precedence diagram in Figure 4.2:

MREGC5003 Industrial Techniques In Maintenance Management img2

Figure 4.2: Precedence Diagram for AOA Network of Figure 4.1

Note that here we show the critical paths in both figures with a tagged and also denser line.

An ACTIVITY is one step in a programme of work which must have a recognisable start and finish. It may consist of several operations.

In Figure 4.3, activity number L6 (DISMANTLE COMPONENTS) has a duration of 4 days, and must be completed (before) the 5 days required for REPAIR BEARINGS which is activity number L8.

MREGC5003 Industrial Techniques In Maintenance Management img3

Figure 4.3

Activity

Further information can be included in the activity boxes. Open our Library web page and search the catalogue for Project Planning and Control by Lester, an electronic book. Figure 12.1 in Chapter 12 shows one way of showing ES, LS, EF, LF, Total float and Duration. A percentage line can be added across the bottom of a box to show a stage of completion required before the next activity starts.

A disadvantage is that for complex networks the diagram can take a lot of space, and the resulting clutter can hinder quick interpretation.

Some of the other advantages of the precedence method are:

  • each activity is given a unique number, which can be encoded for classification by geographical location, type of work, etc;
  • activity title or descriptions can be given in the boxes, as in Figure 4.3;
  • ‘dummy’ activities are not required;
  • the diagram is simple: so it is easy to follow the planned sequence of work;
  • it is easy to add or take away activities on the network;
  • link lines can have a time duration and this reduces the number of activities which need to be shown for any given project; and
  • link lines can specify different types of activity interdependencies as below in Figure 4.4.
MREGC5003 Industrial Techniques In Maintenance Management img4

Figure 4.4: Summary of Elements

Look at Figures 25 and 26 in the Lilley Reader article for another comparison between appearance of AOA and AON network presentations. (“New methods” in 1985 are now commonplace – aren’t they?)

2. Program evaluation and review technique

2.1 Calculation of probability of meeting target completion dates

Activity

If you need some basic statistics, or just a brush-up, see Meredith and Mantel (2003), Project management: A managerial approach, 5th edition, Wiley). Or, check what the Library has available, in paper or electronic format.

PERT is a statistical approach that was developed to estimate the possible duration of work that is being carried out for the first time. PERT methods take account of activities which are likely to have a wide range of durations and costs. How should time be assigned? On the basis of the lowest possible cost, the shortest time, or something else?

The vertical scale in the sketches of Figure 4.5 is the number of data points at each value.

These would form a stepped chart, but if enough values are used, a smooth curve results. The left “most likely” plot is called the Normal Distribution. The peak of this symmetrical bell-shaped curve shows the mean of the distribution. Many random variables, data sets and distributions can be approximated as normal distributions.

However, life in the maintenance world is not always like that, and the spread of times to completion is often likely to be a skewed distribution, as in the other two curves in Figure 4.5.

PERT uses probability theory to measure the probability of achieving predicted durations in terms of “most likely”, “optimistic” and “pessimistic” time estimates. It is clear that the “optimistic” and the “pessimistic” time should occur least often and the “most likely” time should occur most often. Thus it is assumed that the most likely time represents the peak or modal value of a probability distribution; however it can move between the two extremes. These characteristics are best described by the Beta distribution.

MREGC5003 Industrial Techniques In Maintenance Management img5

Figure 4.5

Distribution Curves (a) Normal bell-shaped, (b) and (c) beta distributions, skewed.

In a Normal or bell shaped curve (a), the most likely time is the expected time. In the skewed distribution, the PERT developers came up with this approximation for the expected time, te, as the weighted average given by

MREGC5003 Industrial Techniques In Maintenance Management img6

…and will lie to the right or left of the most likely value, depending on the three time figures. Studies show the error involved calculating te in a Beta distribution is negligible in most industrial applications (e.g. Thierauf and Klekamp (1975), Decision making through operations research, Wiley).

If the duration of an activity is known with certainty, then a = m = b. It is also possible that a = m, and further that m = b. The beta distribution handles all of these extremes.

How reliable are these three estimates? The Delphi method is one way of combining the independent views of several people. In this application, each is asked independent of being influenced by the opinion of others. The mean in each category is used as the best estimate.

Recall that the standard deviation is a measure of the relative spread of a probability distribution about its mean. The difference between a and b is the widest possible overall duration of a project, and is close to ± 3 standard deviations, or one sixth of its range, giving

MREGC5003 Industrial Techniques In Maintenance Management img7

(The variance, another measure of the uncertainty, is the square of the standard deviation).

MSProject uses these terms in PERT to calculate the “Duration” (we call this the expected time te):

  • Optimistic: (best case)
  • Expected: we call this “Most likely”
  • Pessimistic: (worst case)

The default PERT weighting is 1-4-1, but MSProject allows you to change this. For example, use of 1-3-2 weighting gives a little more pessimism for better risk management.

Note also that there are some difficulties with PERT (Winston, 1994). It is assumed that activity durations are independent, but this may be hard to justify. The durations may not follow a beta distribution. The critical path found by CPM may alter, for example, if an activity was delayed, and another completed ahead of schedule, the critical path will alter. Advance methods can be applied, such as Monte Carlo simulation.

If you want another view on statistics, Patrick O’Connor, author of the textbook we use in the reliability engineering units, wrote a tutorial based on the book: Variation in Reliability and Quality. You can see it via the Library electronic journals under “Q” Quality and Reliability Engineering International, 2004: 20:807-821.

The statistics provide clues. They do not provide explanations. Statistical results should be taken into account but engineering knowledge must always provide the ultimate basis for decisions. The use of statistical confidence and significance in engineering applications is seldom useful and is often misleading”. (O’Connor)

Now we shall see how we can make practical use of this.

2.2 Probability of finishing a project in a nominated time period

The central limit theorem in statistics can be applied to a PERT network. Here, where a series of activities that are independent and in sequence lie on the critical path, the sum of the individual activity durations will closely form a normal distribution. The mean of the distribution of the sum of the durations will be the sum of the mean of the activities and its variance will be the sum of the variances.

As the shape of the curve is defined by two parameters: its mean and standard deviation (sigma), the area under the normal curve depends on them too. The total area under the curve equals 1, and the area under a vertical section between two points represents the probability that the variable will be between these two points.

This means that the standard normal distribution table can be used to determine the chance of completing a project within any given time period. A z-transformation is required for finding the area, z being the number of standard deviations. We will now see how to do this using a function in EXCEL, and also using statistical tables.

MREGC5003 Industrial Techniques In Maintenance Management img8

Figure 4.6: Normal Distribution and Central Limit Theorem

Finding probability using EXCEL’s statistical functions

The NORMSDIST function in EXCEL is used. (These steps may vary according to your version of EXCEL - check HELP). Example: What is the probability for a z of 1.1?

  • Click on the function wizard: the “= “ sign)
  • Type in “NORMSDIST(1.1)”.

The area under the normal curve to the left of z (0.8643) will result.

Activity

As we are assuming that the completion time for a project is normally distributed, there is a:

  • 1% chance of completing a project within the time period equal to the mean +1 standard deviation. (Take z = 1);
  • 3% chance that the project will be finished within  1 standard deviations of the mean estimated completion time. This is found by taking z = +1, with the area to left = 0.8413 as before, and for z = –1, area to left = 0.1587. The difference is 0.683, or 68.3%;
  • 4% chance of completing the project within  2 standard deviations of the mean. Confirm this figure yourself;
  • 99% chance of completing within  3 standard deviations. Confirm this figure yourself.

The difference between the most pessimistic and most optimistic time estimates may be approximated as  3 standard deviations. (Does “Six Sigma” ring a bell?)

Finding probability using table of normal distribution

Note that the table following only gives values for up to the right hand half of the curve (i.e. positive values of z).

  • 1% chance of completing a project within the time period equal to the mean +1 standard deviation. (Take z = 1, read off value.)
  • 3% chance that the project will be finished within  1 standard deviations of the mean estimated completion time. This is found by taking z = +1, with the area to left = 0.8413 as before, and for z = –1, area to left = 1 – 0.8413 = 0.1587. The difference in area is 0.683, or 68.3%.
  • 4% chance of completing the project within 2 standard deviations of the mean. Confirm this figure yourself using the table.
  • 99% chance of completing within 3 standard deviations. Confirm this figure yourself using the table.

AREA (z) UNDER THE NORMAL CURVE OF THE LEFT OF z

z

0.00

0.01

0.02

0.03

0.04

0.05

0.06

0.07

0.08

0.09

.0

.1

.2

.3

.4

.5

.6

.7

.8

.9

1.0

.5000

.5398

.5793

.6179

.6554

.6915

.7257

.7580

.7881

.8159

.8413

.5040

.5438

.5832

.6217

.6591

.6950

.7291

.7611

.7910

.8186

.8438

.5080

.5478

.5871

.6255

.6628

.6985

.7324

.7642

.7939

.8212

.8461

.5120

.5517

.5910

.6293

.6664

.7019

.7357

.7673

.7973

.8238

.8485

.5160

.5557

.5948

.6331

.6700

.7054

.7389

.7704

.7995

.8264

.8508

.5199

.5596

.5987

.6368

.6736

.7088

.7422

.7734

.8023

.8289

.8531

.5239

.5636

.6026

.6406

.6772

.7123

.7454

.7764

.8051

.8315

.8554

.5279

.5675

.6064

.6443

.6808

.7057

.7486

.7794

.8078

.8340

.8577

.5319

.5714

.6103

.6480

.6844

.7190

.7517

.7832

.8106

.8365

.8599

.5359

.5753

.6141

.6517

.6879

.7224

.7549

.7852

.8133

.8389

.8621

z

0.00

0.01

0.02

0.03

0.04

0.05

0.06

0.07

0.08

0.09

1.1

1.2

1.3

1.4

1.5

1.6

1.7

1.8

1.9

2.0

2.1

2.2

2.3

2.4

2.5

2.6

2.7

2.8

2.9

3.0

3.1

3.2

3.3

3.4

.8643

.8849

.9032

.9192

.9332

.9452

.9554

.9641

.9713

.9772

.9821

.9861

.9893

.9918

.9938

.9953

.9965

.9974

.9981

.9987

.9990

.9993

.9995

.9997

.8665

.8869

.9049

.9207

.9345

.9463

.9564

.9649

.9719

.9778

.9862

.9864

.9896

.9920

.9940

.9955

.9966

.9975

.9982

.9987

.9991

.9993

.9995

.9997

.8686

.8888

.9066

.9222

.9357

.9474

.9573

.9656

.9726

.9788

.9834

.9871

.9901

.9925

.9943

.9957

.9968

.9977

.9983

.9988

.9991

.9994

.9996

.9997

.8708

.8907

.9082

.9236

.9370

.9484

.9582

.9664

.9732

.9788

.9834

.9871

.9901

.9925

.9943

.9957

.9968

.9977

.9983

.9988

.9991

.9994

.9996

.9997

.8729

.8925

.9099

.9251

.9382

.9495

.9591

.9671

.9738

.9793

.9838

.9875

.9904

.9927

.9945

.9959

.9969

.9977

.9984

.9988

.9992

.9994

.9996

.9997

.8749

.8944

.9115

.9265

.9394

.9505

.9599

.9678

.9744

.9798

.9842

.9878

.9906

.9929

.9946

.9960

.9970

.9978

.9984

.9989

.9992

.9994

.9996

.9997

.8770

.8962

.9131

.9279

.9406

.9515

.9608

.9686

.9750

.9803

.9846

.9881

.9909

.9931

.9948

.9961

.9971

.9979

.9985

.9989

.9992

.9995

.9996

.9997

.8790

.8980

.9147

.9292

.9418

.9525

.9616

.9693

.9756

.9808

.9850

.9884

.9911

.9932

.9949

.9962

.9972

.9979

.9985

.9989

.9992

.9995

.9996

.9997

.8810

.8997

.9162

.9306

.9429

.9535

.9625

.9699

.9761

.9812

.9854

.9887

.9913

.9934

.9951

.9963

.9973

.9980

.9986

.9990

.9993

.9995

.9996

.9997

.8830

.9015

.9177

.9319

.9441

.9545

.9633

.9706

.9767

.9817

.9857

.9890

.9916

.9936

.9952

.9964

.9974

.9981

.9986

.9990

.9993

.9995

.9997

.9998

Activity

Did you repeat the above calculations using the tables?

3. Example 4A: PERT application

Let us now look more closely at how we can use this knowledge in practice. Do remember that even though this method implies precision in its results, all is based on the accuracy of the initial data. Are probabilities finer than to the nearest percentage point valid?

A plant improvement project consists of the activities in the table. The planners have estimated the durations as shown.

What is the probability that the job will be completed within the 28 weeks that have been allocated?

Activity i-j

OptimisticDuration(weeks)

Most LikelyDuration(weeks)

PessimisticDuration(weeks)

1 – 2

1 – 3

1 – 4

2 – 5

3 – 6

4 – 6

4 – 8

5 – 7

6 – 9

7 – 9

8 – 9

3

2

3

4

2

7

4

6

5

2

4

8

5

8

7

3

9

6

9

7

5

6

13

8

10

10

8

10

9

12

11

14

9

Activity

Cover up the next page, and try and sketch out the AOA network for this project.

Solution

The first step in solving this problem is to calculate the expected time and standard deviation on the estimates for each activity on the critical path, using the formulae given earlier:

MREGC5003 Industrial Techniques In Maintenance Management img9

Activity

a

m

b

te

a

1 – 2

1 – 3

1 – 4

2 – 5

3 – 6

4 – 6

4 – 8

5 – 7

6 – 9

7 – 9

8 – 9

3

2

3

4

2

7

4

6

5

2

4

8

5

8

7

3

9

6

9

7

5

6

13

8

10

10

8

10

9

12

11

14

9

8

5

7.5

7

3.6

8.8

6.2

9

7.3

6

6.2

1.7

1

1.17

1

1

0.5

0.83

1

1

2

0.83

These estimated times can now be transferred onto the corresponding activity on the AOA network.

MREGC5003 Industrial Techniques In Maintenance Management img10

Figure 4.7

Here are the possibilities:

1-3-6-9 = 15.9 weeks

1-4-6-9 = 23.6 weeks

1-4-8-9 = 19.9 weeks

1-2-5-7-9 = 30 weeks and as this is the longest path, it is the critical path.

The standard deviation of this time estimate for the critical path is given by:

MREGC5003 Industrial Techniques In Maintenance Management img11

where a = standard deviation of each of the activities on the critical path.

MREGC5003 Industrial Techniques In Maintenance Management img12

But, we want to find the probability of completing the job in 28 weeks. The difference must be obtained terms of standard deviations, so that we can use the statistical tables or the EXCEL functions described above.

30 – 28 = 2 weeks, giving 2 /2.98 = 0.67 standard deviations

i.e. from the normal distribution curve (tables, or EXCEL NORMSDIST)

MREGC5003 Industrial Techniques In Maintenance Management img13

Figure 4.8

The table gives the area under the curve up to the z value. So, the 0.7486 we got applies for 32 weeks. Fig. 4.8 illustrates this. We want the probability of completion in 28 weeks, which is less than the mean, so

Probability of completion in 28 weeks.

= 1 – (probability of completion in 32 weeks).

(Chart is drawn only for entries to the right hand half of the curve. Note that z = 0 (z) = 0.5.)

As already obtained, the probability of completion in 32 weeks is 0.7486.

 Probability of completion in 28 weeks = 25% ANSWER.

4. Example/activity 4B

This example is along similar lines to Example 4A, but is incomplete.

A maintenance contractor wants to complete work on a critical item of plant in 24 hours. If the work can be completed in that time there will be a lucrative bonus payment.

PERT techniques are to be used to schedule and control the outstanding work program.

Table 1 below lists the 11 major activities to be completed and their estimated durations.

What is the probability that the program will be completed within 24 hours?

Activity

OptimisticDuration(hours)

Most LikelyDuration(hours)

Pessimistic Duration(hours)

1-2

3

8

12

1-3

4

7

10

1-4

3

5

10

2-5

2

4

8

3-6

2

3

5

4-6

5

7

8

4-8

3

5

8

5-7

5

8

11

6-9

4

6

10

7-9

2

6

14

8-9

4

5

9

Table 1

Follow the steps as before in Example 4A. If you do not get an answer of 16%, you need to check and see why not!

An important point is that if you decide to have a safety margin, this should only be added to the critical path, and at one place, not at every activity separately.

5. Activity 4C

Activity

Try this problem below by yourself, then check again independently to compare your answer.

You are the Maintenance Manager, and your planner has been working on an upcoming outage. She shows you this table of the list of activities, each with their durations. “I reckon that we can do it in 36 weeks, with a probability of 99%” she says. If you do agree, what duration would you suggest? Draw the network.

Activity i - j

OptimisticDuration(weeks)

Most LikelyDuration(weeks)

PessimisticDuration(weeks)

1-2

2

7

8

2-3

5

6

9

2-4

3

7

8

2-5

4

5

6

3-6

6

9

10

4-7

6

8

11

5-7

4

6

7

6-8

5

7

10

7-8

4

8

9

8-9

4

7

9

6. Crashing networks – time/cost optimisation

Reduction of the activity times is often desirable so as to make up for time lost through unforeseen delays and breakdowns. This reduction can only be achieved at additional cost, through the need for overtime, additional equipment, etc.

To reduce the project time, critical activity times must be reduced. This could result in previously non critical activities forming new or additional critical paths. As activities represent independent phases of work, relative costs will vary according to the nature and quantity of resources required. Hence there is a need to consider which activities will involve the least cost for each reduction of unit time.

The basic procedure of PERT cost optimisation is based upon the preparation of time-cost data for each activity of a network. Using this information a sequence of alternate analysis and re-scheduling of activities is used to determine the optimum cost relationship.

6.1 Activity time/cost data

Estimates of activity cost are usually made on a “most economical” individual activity basis, and in this case the cost of each activity is referred to as the NORMAL COST.

When reducing the duration of each individual activity there is a limit beyond which no additional allocation of resources will reduce the activity time further. This limit is called the CRASH POINT and the cost to achieve this is called the CRASH COST.

The relationship of time reduction to cost can be considered as linear even though the actual relationship will depend on a number of factors not necessarily applicable to all activities.

Consider Figure 4.9 below which shows an activity with a normal duration of 6 days at a cost of $100. By spending more money on resources, it can be completed in 3 days at a crash cost of $250. This means that each day’s reduction in time costs $50 in this case. Note that it may not be possible to crash every activity in a project, but each one that can be crashed will have a curve of this nature.

MREGC5003 Industrial Techniques In Maintenance Management img14

Figure 4.9

It is possible that only certain durations are feasible. For example, the duration may be three days (crashed) or six days (normal) but not four or five days (because of number of people required, etc). Or, in another situation, it may be possible to schedule a duration anywhere between three days and six days.

Using this approximation any activity can be analysed to ensure that the minimum additional total cost is incurred.

7. Example 4D

Determine the minimum cost of completing the project shown in the shortest possible time using the time/cost data tabulated. (Note: the dollar numbers are for illustration and of course not meant to reflect today’s real costs. Call them thousands if you like!).

The crash cost rate/day is the incremental extra cost divided by the number of days saved, e.g. for Activity 4-6, the rate/day = (320 – 120)  (4-2) = $100/day.

Normal

Crash

Crash cost rate/day $

Activity

Days

Cost $

Days

Cost $

1-2

1-3

1-4

2-5

3-6

4-6

5-6

2

1

3

1

2

4

2

60

25

100

25

30

120

40

1

1

2

1

1

2

1

80

25

150

25

50

320

65

20

-

50

-

20

100

25

Totals

400

715

Note that the total cost of normal working is $400, and if we crashed every activity where this can be done, the cost would total $715.

MREGC5003 Industrial Techniques In Maintenance Management img15

Figure 4.10

If all the activities were crashed, additional expenditure may be incurred on activities not affecting the project duration. On the other hand if only the critical path activities were crashed, the project duration could be determined by a new critical path which became longer than the original critical path we selected to crash.

The procedure is to reduce critical activities progressively until all activities on the critical path are at their crash limit; or until any further reduction of a critical activity will not achieve a similar reduction to the project time. Setting this progressive procedure out in a table format can help.

Project Duration

Obtained by Reducing

Additional Direct Cost

Total Direct Cost

Notes

7 Days

Normal completion time

400

Critical Path is 1-4-6

6 Days

1-4 by 1 day

50

450

4-6 could be crashed, but costs more at $100/day.

1-2 now also critical through activities 1-2, dummy 2-4 and 4-6.

We have two parallel critical paths.

Project cost has risen by $50.

5 Days

4-6 by 1 day

100

550

Two critical paths to consider. 1-2 and 1-4 must both be reduced simultaneously to shorten project duration by 1 day, but activity 1-4 is already at its crash limit. Hence activity 4-6 must be reduced by 1 day at additional cost of $100.

2-5, 5-6 now also critical, so we now have 3 critical paths, i.e. 1-4-6 and 1-2-4-6 and 1-2-5-6.

4 Days

4-6 by 1 day

5-6 by 1 day

100 25

675

Can only be achieved by reducing

4-6 to its crash limit of 2 days and 5-6 to its crash limit of 1 day. A further reduction of 1-2 to 1 day would not reduce project duration. Hence 4 days is the shortest possible duration.

Had all the activities been reduced to their crash limit the project would have cost $715, but by using PERT logic the same result has been achieved at the least possible cost $675.

7.1 Total project cost

Total cost consists of two kinds of expenditure.

Direct cost

Examples of direct costs are wages, overtime, penalty payments, hiring additional equipment, material costs, etc. As the activity duration is reduced direct cost will rise in proportion to the amount of additional resources employed. The graph in Figure 4.11 shows, for our example above, the relationship between direct cost and overall duration.

MREGC5003 Industrial Techniques In Maintenance Management img16

Figure 4.11

Indirect costs

Are those which cannot be attributed to any individual activity but are incurred in the operation of the organisation as a whole, such as accommodation, rental, administration, heating, lighting, interest on capital investment.

These costs are charged to the project as a whole, and increase as the project duration increases. We shall take $50/day in our example, with Figure 4.12 showing the trend, rising continuously from zero at zero time.

MREGC5003 Industrial Techniques In Maintenance Management img17

Figure 4.12

Total costs

These are determined by summing the two lower curves as shown (manually, or with

EXCEL), to result in the top curve of Figure 4.12. You will notice that here the Optimum Cost Schedule occurs on either a 6 or 7 day duration. A total project cost of $750 is involved whether the project is completed in either 6 or 7 days (i.e. $450 + 300 or $450 + $300). Here, indirect costs alone make it economic to crash the project duration to 6 days: the job costs no more to finish 1 day earlier!

By linking costs and duration, the network acquires a flexibility which makes it easier to control. A manager may either manipulate costs to adjust the project completion date, or vary the project completion date in order to minimise cost.

This is a most useful technique for pre-tender planning; especially if the project plan based on normal activity times will exceed the specified contract time. The method would also lead to discovery of the most cost efficient method of bringing a delayed construction contract back on target.

Always remember that when there are two or more critical paths, they must be simultaneously crashed in order to reduce project duration.

8. Activity 4E

The AON network in Figure 4.13 represents the shutdown overhaul of a plant installation. Each day the plant is off line costs $300 (here this is the indirect cost). The table gives a list of activities with normal and crash durations and costs.

Activity

Determine the minimum total cost and the optimum time for the project.

MREGC5003 Industrial Techniques In Maintenance Management img18

Figure 4.13

Activity

Normal

Crash

Cost Rate $/day

Days

Cost $

Days

Cost $

1

16

3000

12

3800

2

6

1200

5

1250

3

9

1300

7

1500

6

9

1500

7

1600

4

17

3300

14

3900

5

11

2400

11

2400

7

20

3800

16

4000

8

18

3300

15

3900

9

14

3000

11

3300

13

12

2400

12

2400

10

17

2500

13

2700

11

14

2100

14

2100

12

12

1800

8

2400

Crashing activities on the critical path increases activity costs but the saving in project duration reduces overall costs. In our exercise, the reduction in overall cost due to reduction in project duration is given as $300/day.

Increases in activity costs due to crashing can be found. Cover up the next table. Figure out the cost rate/day of each activity, and write them in the table above.

Activity

Normal

Crash

Crash Cost Rate $/day

Float

Days

Cost $

Days

Cost $

1*

16

3000

12

3800

200

0

2*

6

1200

5

1250

50

0

3*

9

1300

7

1500

100

0

6*

9

1500

7

1600

50

0

4

17

3300

14

3900

200

7

5

11

2400

11

2400

0

7

7

20

3800

16

4000

50

2

8

18

3300

15

3900

200

2

9*

14

3000

11

3300

100

0

13*

12

2400

12

2400

0

0

10

17

2500

13

2700

50

11

11

14

2100

14

2100

0

11

12

12

1800

8

2400

150

11

31600

Normal duration through critical path 1-2-3-6-9-13 is 66 days.

Activities 5, 11 and 13 cannot be crashed, so their duration and costs are unchanged.

Critical activities have zero float, i.e. activities 1, 2, 3, 6, 9 and 13. Start by crashing the cheapest way the possible critical activities. Here, activities 2 and 6 at $50 per day are the lowest cost. Let us work through progressively. You can modify the network information and critical path/s as we go if you like.

Project Duration

Obtained by Reducing

Additional Direct Cost

TotalDirectCost

Notes

66 days

Normal duration

31600

64 days

Activity 6 by 2 days

2 × 50 = 100

31700

Float of 7 and 8 is now used up, giving a second critical path in parallel: 7-8-9-13, so we need to crash an activity on both critical paths.

63 days

Activities 7 and

2 by 1 day

2 × 50 = 100

31800

Activity 9 is on both critical paths, so crash it.

60 days

Activity 9 by

3 days

3 × 100 = 300

32100

Two critical paths still, one new, so need to crash an activity on each path.

58 days

Activities 7 and

3 by 2 days

2 × 50= 100

2 × 100= 200

32400

Crash an activity on each path.

57 days

Crash activities 7 and 1 by 1 more day each

1 × 200= 200

1× 50 = 50

32650

Note: After all these steps, the only activities on the 2 parallel critical paths yet to be crashed completely are activities 1 and 8, each costing $200 per day extra.

Both would need to be done to shorten the duration. Together the cost is $400 per day which is greater than the available saving of $300 per day and is, therefore, not worthwhile.

Optimal project time is thus 57 days

Using normal activity time, the total cost is $31,600 + 66  300 = $51,400

Crashing, the total cost would be $32650 + (57 x 300) = $49,750

Figure 4.14 shows the plot resulting from entering the data into EXCEL as we did in

Example 4D, using here the cost of lost production as the indirect cost of the project.

MREGC5003 Industrial Techniques In Maintenance Management img19

Figure 4.14: Total Costs for Example 4E

9. Activity 4F

It is time to try by yourself.

The activities for a maintenance job are shown in the table, with durations and estimates of costs. To check the effect of completing the job more quickly, further estimates of crash duration and the resulting higher costs have been made.

Activity

No

rmal

Crash

Crash Cost Rate $/day

Float

(days)

($)

(days)

($)

1-2

5

600

3

800

1-3

4

200

3

400

2-4

3

150

3

150

2-5

2

400

2

400

3-4

7

200

3

500

4-7

3

150

1

250

4-8

5

300

4

400

5-6

6

660

3

900

6-9

5

200

2

500

7-9

7

160

5

210

8-9

4

100

3

130

Calculate:

  • the total cost of both methods of performing the work;
  • the optimised direct cost of carrying out the work in the crash overall duration; and
  • the optimum duration of the job when overheads and other indirect costs of $100 per day are included.

When you have completed your work, try again from scratch. If your answer differs, then check what might be problem and try again.

A table layout, as shown following, helps keep track of each step, and I strongly suggest that you adopt it.

Project Duration

Obtained by Reducing

Additional Direct Cost

Progressive

Total Direct

Cost $

Progressive Total Cost $

Notes

Normal Duration

10. GERT: A conditional sequencing/scheduling method

CPM/PERT analysis methods do not allow network loops (e.g. a project test that may be repeated more than once) or conditional branches (e.g. a design upgrade that occurs only if an inspection detects errors) in their sequenced networks. GERT (graphical evaluation and review technique) is a diagramming method that “combines signal flowgraph theory, probabilistic networks, CPM/PERT, and decision trees all in a single framework” (Meredith and Mantel, 1995).

GERT utilises complex probabilistic and branching nodes. These nodes can specify both the number of activities leading to them which must be realised, and the potential multiple branching paths that can emanate from them. When each branching activity has an assigned probability of occurrence, the sum of the probabilities over all the branches is 1.0. When no probabilities are assigned for the branches, it is automatically assumed that the probability is 1.0 for each branch (i.e. every branch must be taken).

Typical GERT node nomenclature has been extracted from Nicholas, J.M. (1990), Managing business and engineering projects, Prentice-Hall, Englewood Cliffs, and is shown in Figure 4.15:

MREGC5003 Industrial Techniques In Maintenance Management img20

Figure 4.15: GERT Node Nomenclature

Figure 4.15(a) represents a node that can be reached the first time by completing any two (top left hand quadrant) of the input activities a, b, or c. If the node is reached again (through looping), only one of a, b, or c need be completed (refer lower left hand quadrant). When the node is reached, both activities d and e can commence.

Figure 4.15(b) signifies that all preceding activities (a and b) must be completed before the node is reached. The infinity symbol means that the node cannot be subsequently reached (i.e. no network loops are permitted back to it). When the node is reached, activities c, d, or e will commence with probabilities of occurrence of 0.3, 0.4, and 0.3, respectively.

A comparison of GERT and CPM/PERT characteristics is illustrated in this table (adapted from Meredith and Mantel, 1995):

GERT Characteristics

CPM/PERT Characteristics

Branching from a node is probabilistic

Branching from a node is deterministic

Various probability distributions for time estimates are possible

Only the beta probability distribution for time estimates is possible

Flexibility in node realisation is possible

No flexibility in node realisation is possible

Looping back to earlier events is acceptable

Looping back is not permitted

Difficult to use as a control tool

Simple to use for control

Arcs may represent time, cost, reliability, etc

Arcs represent time only

I suggest that you should always aim to adopt the simplest sequencing/scheduling technique that is consistent with the needs of your project. While a thorough GERT analysis can be more comprehensive than the simpler CPM/PERT analyses, both the input information and the computational requirements are far more extensive for a GERT analysis.

Next up, we consider outage management as a special case of project management.