Develop a network diagram for the project. Identify the critical path for the project. What is the overall project duration in weeks?
Assume you have presented the above diagram and project duration to the client. The client has asked you to reduce the schedule by 2 weeks. How can you manipulate your schedule to achieve this reduction? You may not reduce the durations of the activities.