WX Camel, the well-known real estate developer, worked long hours, and he expected his staff to do the same. So Jean Chavez was not surprised to receive a call from the boss just as Jean was about to leave for a long summer’s weekend.

 

Mr. Camel’s success had been built on a remarkable instinct for a good site. He would exclaim “Location! Location! Location!” at some point in every planning meeting. Yet finance was not his strong suit. On this occasion he wanted Jean to go over the figures for a new $90 million  outlet mall designed to intercept tourists heading downeast toward Mary. “First thing Monday will do just fine,” he said as he handed Jean the file. “I’ll be in my house in Bar Harbor if you need me.”

 

Jean’s first task was to draw up a summary of the projected revenues and costs. The results are shown in Table 1. Note that the mall’s revenues would come from two sources: The company would charge retailers an annual rent for the space they occupied and in addition it would receive 5% of each store’s gross sales.

 

Construction of the mall was likely to take three years. The construction costs could be depreciated straight-line over 15 years starting in year 3. As in the case of the company’s other developments, the mall would be built to the highest specifications and would not need to be rebuilt until year 17. The land was expected to retain its value, but could not be depreciated for tax purposes.

 

Construction costs, revenues, operating and maintenance costs, and real estate taxes were all likely to rise in line with inflation, which was forecasted at 2% a year. The company’s tax rate was 35% and the cost of capital was 9% in nominal terms.

 

Jean decided first to check that the project made financial sense. He then proposed to look at some of the things that might go wrong. His boss certainly had a nose for a good retail project, but he was not infallible. The Salome project had been a disaster because store sales had turned out to be 40% below forecast. What if that happened here? Jean wondered just how far sales could fall short of forecast before the project would be underwater. 

 

Inflation was another source of uncertainty. Some people were talking about a zero long-term inflation rate, but Jean also wondered what would happen if inflation jumped to, say, 10%. 

 

A third concern was possible construction cost overruns and delays due to required zoning changes and environmental approvals. Jean had seen cases of 25% construction cost overruns and delays up to 12 months between purchase of the land and the start of construction. He decided that he should examine the effect that this scenario would have on the project’s profitability.

 

“Hey, this might be fun,” Jean exclaimed to Mr. WX’s secretary, Fifi, who was heading for Old Orchard Beach for the weekend. “I might even try Monte Carlo.”

 

“WX went to Monte Carlo once,” Fifi replied.

 

“Lost a bundle at the roulette table. I wouldn’t remind him. Just show him the bottom line. Will it make money or lose money? That’s the bottom line.”

 

“OK, no Monte Carlo,” Jean agreed. But he realized that building a spreadsheet and running

scenarios was not enough. He had to figure out how to summarize and present his results to Mr. Camel.

 

 

Year

 

0

1

2

3

4

5-17

Investment

· Land

· Construction

 

30

20

 

 

30

 

 

10

 

 

 

Operations:

· Rentals

· Share of retail sales

· Operating and maintenance costs

· Real estate taxes

 

 

 

 

 

2

 

 

2

 

 

 

 

 

4

 

 

2

 

 

 

 

 

4

 

 

3

 

12

24

 

 

10

 

 

4

 

12

24

 

 

10

 

 

4

 

12

24

 

 

10

 

 

4

Table 1: Projected revenues and costs in real term for the Downeast Tourist Mall (figures in MYR million)

 

QUESTIONS:

 

1. What is the project’s NPV, given the projections in Table 1 ?

2. Conduct a sensitivity and a scenario analysis of the project. What do these analyses reveal about the project’s risks and potential value?

 

 

ocked="false" Priority="99" SemiHidden="false" Name="heading 9" > <br /> </article> <img src="https://www.urgenthomework.com/webimg/uah/question/ width="10"> Read less

Buy Fin544 Finance|Real Estate Developer Assessment Answers Online


Talk to our expert to get the help with Fin544 Finance|Real Estate Developer Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Fin544 Finance|Real Estate Developer Assessment Answer Assignment Help Online

Resources

    • 24 x 7 Availability.
    • Trained and Certified Experts.
    • Deadline Guaranteed.
    • Plagiarism Free.
    • Privacy Guaranteed.
    • Free download.
    • Online help for all project.
    • Homework Help Services
); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.