Epm5620 Project Management And Business Assessment Answers

Questions:

This assignment follows from the case study used in Assessment 2. For the same case study, complete the following tasks by creating the following:
1. WBS first using indented format.
2.Gantt chart-Take the WBS you have already developed. Define all of the activities that will be necessary to create each deliverable in your WBS. Create a schedule for your project. First create the schedule by hand using Post-it Notes, and then put the information into MS Project. Take screenshots of the schedule to be pasted in your word document that you are submitting. Be sure to include all of the summary rows (including the first row for the project title) and any key milestones. Make sure the critical path is easy to see.
3.Create a time-phased budget for your example project using bottom-up estimating. To the extent your sponsor will supply rates for workers, use those. Approximate rates for ones you cannot get. Ask your sponsor how they treat indirect costs. Be sure to include direct labour costs for you and your team mates and add 20% for fringe. State all assumptions and constraints you have used when creating your budget. State how confident you are in your estimates and what would make you more confident. Give examples of known knowns and known unknowns on your project. Tell how you have budgeted for both of them plus how you have budgeted for unknown unknowns.
4.Create a risk register ( 4 risks- 3 negative and 1 positive risk)for your example project.
5.Quality Management Plan. It should include:
A short statement that reflects your team’s philosophy or objective for ensuring that you deliver a quality system to your client.
Develop and describe 3 quality issues related to this project that your project team could implement to ensure quality
Closure checklist and project evaluation. :
Develop a closure checklist that the project team will use to ensure that the project has been closed properly.
Develop a project evaluation outline and discuss how your project’s MOV will be evaluated.

Answers:

Introduction

The Project management plays a crucial role in the development of the project functions and operations of the organization. It is important for developing the smart functions of the project operations with the help of project management tools and techniques. The development of project management had been done for assisting in the operations of the project and development of smart functionalities of operations.

The following report had been developed for forming the accurate development of project operations and development of systematic functions in the organization. The Social Media Research Centre had been longing to develop a web based application for improving their operations and functions. It would help in easing their operations and functions. The report would use project management tools and concepts for analysing the various functions of the project.

1. Indented WBS

WBS

Task Name

0

Web Application Development for SRC

1

   Initialization Phase

1.1

      Requirement Analysis

1.2

      Selecting Business Model

1.3

      Making Charter Documents

1.4

      Proposal is Passed

2

   Planning Phase

2.1

      Meetings are being held

2.2

      Model of operation is selected

2.3

      Plan outline is developed

2.4

      Objectives of plan is aligned

2.5

      Plan is approved

3

   Web Application is developed

3.1

      Designing of application

3.1.1

         Selection of design platform

3.1.2

         UX style is developed

3.1.3

         Tools and equipments are selected

3.2

      Database Creation

3.2.1

         Platform of database is selected

3.2.2

         Database design is made

3.2.3

         Storage platform is selected

3.2.4

         Database is integrated and built

3.3

      Application Creation

3.3.1

         Application platform is selected

3.3.2

         Application Programs and Codes are developed

3.3.3

         Database is integrated with application

3.3.4

         Application is developed

3.4

      Web Functionality deployment

3.4.1

         URL, CSS, and Java Script is developed

3.4.2

         Error 404 page is developed

3.4.3

         Web Function is developed

3.5

      Testing Phase

3.5.1

         Application Testing

3.5.2

         UX is reviewed

3.5.3

         Calibaration testing

3.5.4

         Typography testing

3.6

      Training Phase

3.6.1

         Training Manuals are created

3.6.2

         Training is being given

4

   Project Closure

4.1

      Final Documents are made

4.2

      Documents are signed

4.3

      Project is closed

2. Gantt Chart for Project

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

0

Web Application Development for SRC

152 days

Mon 4/3/17

Tue 10/31/17

 

 

$49,920.00

1

   Initialization Phase

16 days

Mon 4/3/17

Mon 4/24/17

 

 

$4,920.00

1.1

      Requirement Analysis

5 days

Mon 4/3/17

Fri 4/7/17

 

System Analyst

$1,400.00

1.2

      Selecting Business Model

4 days

Mon 4/10/17

Thu 4/13/17

2

Program Manager

$1,440.00

1.3

      Making Charter Documents

5 days

Fri 4/14/17

Thu 4/20/17

3

Team Member

$1,200.00

1.4

      Proposal is Passed

2 days

Fri 4/21/17

Mon 4/24/17

4

Project Manager

$880.00

2

   Planning Phase

23 days

Tue 4/25/17

Thu 5/25/17

 

 

$8,120.00

2.1

      Meetings are being held

10 days

Tue 4/25/17

Mon 5/8/17

5

Project Manager

$4,400.00

2.2

      Model of operation is selected

4 days

Tue 5/9/17

Fri 5/12/17

7

Team Member

$960.00

2.3

      Plan outline is developed

3 days

Mon 5/15/17

Wed 5/17/17

8

Program Manager

$1,080.00

2.4

      Objectives of plan is aligned

4 days

Thu 5/18/17

Tue 5/23/17

9

Team Member

$960.00

2.5

      Plan is approved

2 days

Wed 5/24/17

Thu 5/25/17

10

Program Manager

$720.00

3

   Web Application is developed

105 days

Fri 5/26/17

Thu 10/19/17

 

 

$34,200.00

3.1

      Designing of application

12 days

Fri 5/26/17

Mon 6/12/17

 

 

$3,840.00

3.1.1

         Selection of design platform

4 days

Fri 5/26/17

Wed 5/31/17

11

Graphic Designer

$1,280.00

3.1.2

         UX style is developed

5 days

Thu 6/1/17

Wed 6/7/17

14

Graphic Designer

$1,600.00

3.1.3

         Tools and equipments are selected

3 days

Thu 6/8/17

Mon 6/12/17

15

Graphic Designer

$960.00

3.2

      Database Creation

20 days

Tue 6/13/17

Mon 7/10/17

 

 

$6,400.00

3.2.1

         Platform of database is selected

4 days

Tue 6/13/17

Fri 6/16/17

16

Database Manager

$1,280.00

3.2.2

         Database design is made

5 days

Mon 6/19/17

Fri 6/23/17

18

Database Manager

$1,600.00

3.2.3

         Storage platform is selected

4 days

Mon 6/26/17

Thu 6/29/17

19

Database Manager

$1,280.00

3.2.4

         Database is integrated and built

7 days

Fri 6/30/17

Mon 7/10/17

20

Database Manager

$2,240.00

3.3

      Application Creation

23 days

Tue 7/11/17

Thu 8/10/17

 

 

$9,200.00

3.3.1

         Application platform is selected

4 days

Tue 7/11/17

Fri 7/14/17

21

Application Programmer

$1,600.00

3.3.2

         Application Programs and Codes are developed

10 days

Mon 7/17/17

Fri 7/28/17

23

Application Programmer

$4,000.00

3.3.3

         Database is integrated with application

5 days

Mon 7/31/17

Fri 8/4/17

24

Application Programmer

$2,000.00

3.3.4

         Application is developed

4 days

Mon 8/7/17

Thu 8/10/17

25

Application Programmer

$1,600.00

3.4

      Web Functionality deployment

16 days

Fri 8/11/17

Fri 9/1/17

 

 

$4,480.00

3.4.1

         URL, CSS, and Java Script is developed

7 days

Fri 8/11/17

Mon 8/21/17

26

Web System Analyst

$1,960.00

3.4.2

         Error 404 page is developed

5 days

Tue 8/22/17

Mon 8/28/17

28

Web System Analyst

$1,400.00

3.4.3

         Web Function is developed

4 days

Tue 8/29/17

Fri 9/1/17

29

Web System Analyst

$1,120.00

3.5

      Testing Phase

19 days

Mon 9/4/17

Thu 9/28/17

 

 

$6,080.00

3.5.1

         Application Testing

5 days

Mon 9/4/17

Fri 9/8/17

30

Quality Expert

$1,600.00

3.5.2

         UX is reviewed

4 days

Mon 9/11/17

Thu 9/14/17

32

Quality Expert

$1,280.00

3.5.3

         Calibration testing

5 days

Fri 9/15/17

Thu 9/21/17

33

Quality Expert

$1,600.00

3.5.4

         Typography testing

5 days

Fri 9/22/17

Thu 9/28/17

34

Quality Expert

$1,600.00

3.6

      Training Phase

15 days

Fri 9/29/17

Thu 10/19/17

 

 

$4,200.00

3.6.1

         Training Manuals are created

5 days

Fri 9/29/17

Thu 10/5/17

35

Program Manager

$1,800.00

3.6.2

         Training is being given

10 days

Fri 10/6/17

Thu 10/19/17

37

Team Member

$2,400.00

4

   Project Closure

8 days

Fri 10/20/17

Tue 10/31/17

 

 

$2,680.00

4.1

      Final Documents are made

5 days

Fri 10/20/17

Thu 10/26/17

38

Program Manager

$1,800.00

4.2

      Documents are signed

2 days

Fri 10/27/17

Mon 10/30/17

40

Project Manager

$880.00

4.3

      Project is closed

1 day

Tue 10/31/17

Tue 10/31/17

41

 

$0.00

3. Time Phase Budget

The resource usage with passage of time are shown in the table below,

Resource Name

Work

Cost

Application Programmer

184 hrs

$9,200.00

   Application platform is selected

32 hrs

$1,600.00

   Application Programs and Codes are developed

80 hrs

$4,000.00

   Database is integrated with application

40 hrs

$2,000.00

   Application is developed

32 hrs

$1,600.00

Database Manager

160 hrs

$6,400.00

   Platform of database is selected

32 hrs

$1,280.00

   Database design is made

40 hrs

$1,600.00

   Storage platform is selected

32 hrs

$1,280.00

   Database is integrated and built

56 hrs

$2,240.00

Graphic Designer

96 hrs

$3,840.00

   Selection of design platform

32 hrs

$1,280.00

   UX style is developed

40 hrs

$1,600.00

   Tools and equipments are selected

24 hrs

$960.00

Project Manager

112 hrs

$6,160.00

   Proposal is Passed

16 hrs

$880.00

   Meetings are being held

80 hrs

$4,400.00

   Documents are signed

16 hrs

$880.00

Program Manager

152 hrs

$6,840.00

   Selecting Business Model

32 hrs

$1,440.00

   Plan outline is developed

24 hrs

$1,080.00

   Plan is approved

16 hrs

$720.00

   Training Manuals are created

40 hrs

$1,800.00

   Final Documents are made

40 hrs

$1,800.00

Team Member

184 hrs

$5,520.00

   Making Charter Documents

40 hrs

$1,200.00

   Model of operation is selected

32 hrs

$960.00

   Objectives of plan is aligned

32 hrs

$960.00

   Training is being given

80 hrs

$2,400.00

System Analyst

40 hrs

$1,400.00

   Requirement Analysis

40 hrs

$1,400.00

Web System Analyst

128 hrs

$4,480.00

   URL, CSS, and Java Script is developed

56 hrs

$1,960.00

   Error 404 page is developed

40 hrs

$1,400.00

   Web Function is developed

32 hrs

$1,120.00

Quality Expert

152 hrs

$6,080.00

   Application Testing

40 hrs

$1,600.00

   UX is reviewed

32 hrs

$1,280.00

   Calibration testing

40 hrs

$1,600.00

   Typography testing

40 hrs

$1,600.00

The assumptions of the project are,

Resources: The project had been developed considering that the resources of the project are easily available for use. The project would allow an exhaustion of AUD 50000 as the budget and all the resources would be managed within the budget amount. The human resources have a fixed salary and they have been allocated work according to their activities.

Time: The project has a timeline of working duration for less than 8 months. The project would commence on first working Monday of April that is on 3rd April and continue with 5 working days a week and 8 hours a day to end the project till 31st October. The total number of days for which the project would work about is 152 days.

The constraints of the project are,

Technology Dependent: The project activities are dependent on the support of the technology and technical skills. The deployment of web based application is being made with the help of technological development and tools.

Quality: Quality of web application operations is another factor that forms the development of the project operations in the organization. The quality of the operations are being managed and rummaged for ensuring the application of website in the organization.

Budget Estimation: The budget estimation for the project is being done for realizing the activities of the project in terms of cost and resource expense. The direct costs of materials, salaries of person involved, and other expenses have been considered for developing the project cost. These direct costs and expenses are the known knowns of the project and they are allocated the resources by the help of the ms-project software and the budget allocation option. The unknowns in the project are the risk factors and over budgeted operations that cannot be overlooked. However, provisional planning would help in developing the effective planning of the project operations.

The list of resource rates is give below,

Resource Name

Initials

Std. Rate

Application Programmer

A

$50.00/hr

Database Manager

D

$40.00/hr

Graphic Designer

G

$40.00/hr

Project Manager

P

$55.00/hr

Program Manager

PM

$45.00/hr

Team Member

T

$30.00/hr

System Analyst

S

$35.00/hr

Web System Analyst

W

$35.00/hr

Quality Expert

Q

$40.00/hr

4. Risk Register

No.

RFDT_001

RFCI_002

RFOB_003

RFEF_004

Rank

First

Second

Third

Fourth

Risk

Data Theft

Complexity of integration

Over budget and resource exhaustion

Early finishing of project

Description

External Infiltration in the Application system for extracting information from the database

Different requirements of different platforms of the web utilization

Project activities might exhaust more resources than expected

The project would be completed before the expected time

Category

Negative- Technical

Negative- Performance

Negative- Finance

Positive- Performance

Root Cause

Security flaw

Flaw in integration design

Excess utilization of resources

Faster processes of the project

Triggers

Cyber Criminals or hackers

Complex structure of application platform

Issues in completing any particular project activity

Smart project plan

Risk Response

Developing security features and implementing them

Integrated operations considering platform independent activities should be implied

Provisional budget allocation should be made

Exploit the risk for reviewing the application

Risk Owner

Security Designer

Designer of Application

Budgeter

Project Manager

Probability

Likely

Likely

Possible

Possible

Impact

Severe

Major

Major

Minor

5. Quality Management Plan

The assurance statement for the project had been given below,

  • To develop a project plan that would be suitable for the development of web application for the Social Media Research Centre.
  • To ensure that all requirements of the project operations have been developed as per the clients’ needs

3 quality issues of the project

  1. Security issue: The security issue is the most dominant factor that would cause harm for the processes of the project operation
  2. Performance issue: Unable to integrate the operations of the project is being another major quality issue for the project
  3. Technical issue: The network connection being absent would also serve the issue of the project

6. Closure Checklist and Evaluation of Project

Project Name: “Web Application Development for SRC”

Document: Closure Checklist

Created By: Team Member

Dated: 5th November, 2017

Checklist Items:

The project plan is developed

The design of application is made

The database is created

The design of the website is made

The web functions is added to the application

Various tests have been done on the application

Documentation is completed

Signed off by Project Manager

 

þ

þ

þ

þ

þ

þ

þ

þ

Signed off:

..............

<name of the student>

Project Manager

Project Evaluation: The project would be evaluated in terms of the profit margin for the project. The development strategies would be managed for finding out the operations of the project. NPV, Payback Period, and IRR could be used for evaluating the project. Specific, Measurable, Attainable, Repetitive, and Timely are the Smart functionality testing of the project.

Conclusion

The created report had been produced for framing the exact improvement of venture operations and advancement of efficient capacities in the association. The Social Media Research Centre had been yearning to build up an online application for enhancing their operations and capacities. It would help in facilitating their operations and capacities. The report had utilized the extended administration apparatuses and ideas for examining the different elements of the venture. The Project administration had assumed a significant part in the improvement of the venture capacities and operations of the association. It can be concluded that the development of the brilliant elements of the venture operations with the assistance of venture administration devices and systems. The improvement of venture administration had been accomplished for aiding the operations of the venture and advancement of shrewd functionalities of operations.

Bibliography

Fewings, P. (2013). Construction project management: an integrated approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.

Heizer, R., & Barry, R. (2013). Operation Management, Sustainability and Supply Chain management (Vol. 11). Pearson, UK.

Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Meier, K. M., & Deep Vadose Zone Applied Field Research Initiative. (2015). Quality assurance plan.

Newton, R. (2016). Project management step by step: how to plan and manage a highly successful project. Pearson UK.

Rees-Caldwell, K., & Pinnington, A. H. (2013). National culture differences in project management: Comparing British and Arab project managers' perceptions of different planning areas. International Journal of Project Management, 31(2), 212-227.

Sallis, E. (2014). Total quality management in education. Routledge.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Turner, R. (2016). Gower handbook of project management. Routledge.

Walker, A. (2015). Project management in construction. John Wiley & Sons.

Yarwood, G., Guenther, A., de Gouw, J., & Parrish, D. (2014). Quality Assurance Project Plan Project 14-016 Improved Land Cover and Emission Factor Inputs for Estimating Biogenic Isoprene and Monoterpene Emissions for Texas Air Quality Simulations.


Buy Epm5620 Project Management And Business Assessment Answers Online


Talk to our expert to get the help with Epm5620 Project Management And Business Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Epm5620 Project Management And Business Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.