Urgenthomework logo
UrgentHomeWork
Live chat

Loading..

Fins5511 Corporate Finance - Computation Assessment Answers

HBP Mining Ltd (HBP) currently operates an iron ore mine and has commissioned GB to determine whether to continue operating the mine or to abandon it. The price of iron ore is currently $55 per ton, with the mine producing 80,000 tons of iron ore per year and costing $5 million per year to operate. In its current state, the mine has enough iron ore to continue operating for 90 years. Shutting the mine down would require HBP to bringing the land up to environmental standards, which is expected to cost $5 million. Reopening the mine once it is shut down would be an impossibility given current environmental standards. 

HBP's risk management department believes that (given current economic conditions) the price of iron ore has a 45% probability of going up by 25%, and 55% probability of going down by 15% every year for the next three years. After three years, economic conditions will have stabilised so that the price of iron ore will remain constant for the remaining life of the mine. They have also estimated HBP's cost of capital to be 12%. 

Requirements:

1. Draw a decision tree to summarise the dilemma faced by HBP.   
2. Calculate the NPV of continuing to operate the mine by working your way backwards through the tree and taking into account the option to abandon.    
3. Based on your answer in (2), what should HBP do with the iron ore mine?   

We ask that you keep all your formulas as simple as possible - don't go overboard and make them unnecessarily complicated. It makes your assignment difficult to understand which can lead to us not allocating you part marks for your effort, particularly if your answer is incorrect! The decision tree can be done in Excel or attached to the report.

Answer 

Corporate Finance: Decision tree and Computation of Net Present Value

Requirement 1

Requirement 2: Computation of NPV

The prices of copper for the year end 1, 2, and 3 have been computed as shown in the decision tree in requirement 1 above. There are eight probable prices of copper finally arrived at the end of year 3, which make eight nodes for the purpose of computation of NPV. The computation of net present values for each node is given as under:

NPV at Node-1

Price of copper in year 1 is $68.75; therefore, the cash inflows will be $5.50 million (80000 tones*$68.75). The company incurs $5 million operating cost. Thus, the net cash flows for year 1 work out to be $0.50 million. In same way, the net cash flows for year 2 are worked out to be $1.88 million and the net cash flows from third year and onwards will be $3.59 million. The project’s life is 90 years, thus, the net cash flows of $3.59 million will accrue for 88 years. Using these figures and cost of capital of 12%, the NPV has been computed as under:

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$68.75

                                    0.50

2

$85.94

                                    1.88

3

$107.42

                                    3.59

4 to 90

$107.42

                                    3.59

 

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

          0.50

                                    0.89

                  0.45

2

          1.88

                                    0.80

                  1.49

3

          3.59

                                    0.71

                  2.56

4 to 90

          3.59

                                    5.93

                21.32

 

 NPV

                25.81

NPV at Node-2

At node-2, the price of copper in year 1 and 2 remains the same as it was at node-1, therefore, the net cash flows will also remain same. However, the price of copper for year 3 and onwards changes to $73.05, which changes the net cash flow also to $0.84 million. The NPV has been computed as under:

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$68.75

                                    0.50

2

$85.94

                                    1.88

3

$73.05

                                    0.84

4 to 90

$73.05

                                    0.84

 

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

          0.50

                                    0.89

                  0.45

2

          1.88

                                    0.80

                  1.49

3

          0.84

                                    0.71

                  0.60

4 to 90

          0.84

                                    5.93

                  5.00

 

 NPV

                  7.55

NPV at Node-3

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$68.75

                                    0.50

2

$58.44

                                  (0.33)

3

$73.05

                                    0.84

4 to 90

$73.05

                                    0.84

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

          0.50

                                    0.89

                  0.45

2

        (0.33)

                                    0.80

                (0.26)

3

          0.84

                                    0.71

                  0.60

4 to 90

          0.84

                                    5.93

                  5.00

 

 NPV

                  5.79

NPV at Node-4

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$68.75

                                    0.50

2

$58.44

                                  (0.33)

3

$49.67

                                  (1.03)

4 to 90

$49.67

                                  (1.03)

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

          0.50

                                    0.89

                  0.45

2

        (0.33)

                                    0.80

                (0.26)

3

        (1.03)

                                    0.71

                (0.73)

4 to 90

        (1.03)

                                    5.93

                (6.09)

 

 NPV

                (6.63)

Since, the net present value to operate mine at this node is $-6.63 million, while, the cost of option to abandon is $5 million. Thus, the company will go for exercising the option to abandon rather than continuing mining operations in this case. Thus, the net present value for this node becomes $-5.00 million.  

NPV at Node-5

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$46.75

                                  (1.26)

2

$58.44

                                  (0.33)

3

$73.05

                                    0.84

4 to 90

$73.05

                                    0.84

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

        (1.26)

                                    0.89

                (1.13)

2

        (0.33)

                                    0.80

                (0.26)

3

          0.84

                                    0.71

                  0.60

4 to 90

          0.84

                                    5.93

                  5.00

 

 NPV

                  4.22

NPV at Node-6

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:           

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$46.75

                                  (1.26)

2

$58.44

                                  (0.33)

3

$49.67

                                  (1.03)

4 to 90

$49.67

                                  (1.03)

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

        (1.26)

                                    0.89

                (1.13)

2

        (0.33)

                                    0.80

                (0.26)

3

        (1.03)

                                    0.71

                (0.73)

4 to 90

        (1.03)

                                    5.93

                (6.09)

 

 NPV

                (8.20)

Since, the net present value to operate mine at this node is $-8.20 million, while, the cost of option to abandon is $5 million. Thus, the company will go for exercising the option to abandon rather than continuing mining operations in this case. Thus, the net present value for this node becomes $-5.00 million.

NPV at Node-7

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:           

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$46.75

                                  (1.26)

2

$39.74

                                  (1.82)

3

$49.67

                                  (1.03)

4 to 90

$49.67

                                  (1.03)

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

        (1.26)

                                    0.89

                (1.13)

2

        (1.82)

                                    0.80

                (1.45)

3

        (1.03)

                                    0.71

                (0.73)

4 to 90

        (1.03)

                                    5.93

                (6.09)

 

 NPV

                (9.39)

Since, the net present value to operate mine at this node is $-9.39 million, while, the cost of option to abandon is $5 million. Thus, the company will go for exercising the option to abandon rather than continuing mining operations in this case. Thus, the net present value for this node becomes $-5.00 million.

NPV at Node-8

In the light of the changes in the price of copper, the computation of net cash flows is given as follows:           

Year

Price

Net cash flows ($M)

 

 

[(Price*80000 tones)-$5M]

1

$46.75

                                  (1.26)

2

$39.74

                                  (1.82)

3

$33.78

                                  (2.30)

4 to 90

$33.78

                                  (2.30)

Considering the above cash flows, the net present value has been computed as under:

Year

Net Cash flow ($M)

PV factor

PV ($M)

1

        (1.26)

                                    0.89

                (1.13)

2

        (1.82)

                                    0.80

                (1.45)

3

        (2.30)

                                    0.71

                (1.64)

4 to 90

        (2.30)

                                    5.93

              (13.63)

 

 NPV

              (17.84)

Since, the net present value to operate mine at this node is $-17.84 million, while, the cost of option to abandon is $5 million. Thus, the company will go for exercising the option to abandon rather than continuing mining operations in this case. Thus, the net present value for this node becomes $-5.00 million.

Now, using the probabilities, the estimated net present value for the company in respect of mining project has been computed in the statement given below:

Node

NPV ($M)

Joint Probability

Expected NPV

1

        25.81

0.091125

                  2.35

2

          7.55

0.111375

                  0.84

3

          5.79

0.111375

                  0.65

4

        (5.00)

0.136125

                (0.68)

5

          4.22

0.111375

                  0.47

6

        (5.00)

0.136125

                (0.68)

7

        (5.00)

0.136125

                (0.68)

8

        (5.00)

0.166375

                (0.83)

 

NPV

                  1.43

Requirement 3

The expected net present value as worked out in requirement 2 given above depicts that the company will be benefited by $1.43 million by undertaking the mining operations. Therefore, it is recommended that the company undertakes the mining operations on the iron ore mine.


Buy Fins5511 Corporate Finance - Computation Assessment Answers Online


Talk to our expert to get the help with Fins5511 Corporate Finance - Computation Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Fins5511 Corporate Finance - Computation Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.