Iscg8022 Managing Information Technology Projects Assessment Answers

Questions:

1.Prepare a business case for implementing a new Cloud based Integrated System covering all operations for Star Car Rentals. Your report should provide a compelling reason for the company’s Management to accept your proposal for implementing the system. Limit your report to one page.

2.Assuming that Sandra has secured approval to implement the system, prepare the following: 
a.The project organization structure – a one page chart
b.The work breakdown structure – a one page chart
c.Your project’s deliverables – provide a list and a one or two line description of each deliverable – one page.
d.The activities required to be performed with effort estimates in terms of person hours, wherever applicable – this may be depicted in a table suitably classified under a few main work streams. The activity list should be comprehensive and should be such that it can be allocated to an individual role.
e.A high level project schedule – your schedule should show major activities with start date, finish date, dependencies and who would be responsible for completing each activity. 
f.The risks that you foresee in implementing this project and the activities that you will undertake to mitigate the effects of these risks - limit this to one page.
g.The quality control activities that you will undertake to ensure that the project’s deliverables are in acceptable condition – limit this to one page.
h.What would be the communication plan for your project? Include appropriate templates with your answer. Provide only bullet points for the Communication Plan. 

Answer:

Introduction

The report is based on implementation of new cloud based integrated system in Star Car Rentals so that their business operations are improved and it leads to increase in market share of the company. There are various issues in the current system of the company which are required to be improved on scheduled time. This particular report analyzes the business case of Star Car Rentals with its business needs and benefits. It also analyzes the project cost to determine the budget for implementation plan. An organization structure and work breakdown structure is analyzed to determine the project team and work activities in this project. The paper analyzes the project schedule to determine start and end date of project, earned value analysis to determine various project cost analysis and risk to identify possible risks in the plan.

Business case of Star Car Rentals

Business needs

Star Car Rentals attained a market share of 45% of New Zealand car rental market with implementation of IT systems to cover its operations in areas such as customer relationship management, vehicle pick up, returns management, accounting, payroll, reservation management and others. The major problem with its existing applications is lack of integration. The current system has problems related to incorrect information about availability of vehicle, poor vehicle maintenance, incorrect invoicing and others. Those problems provide effect on rapid decline in revenue as the customers are moving away from the company. In the year 2018, the market share of company is stood at 20%. There is also reduction in sales as well as fall in the market share of the company. In order to overcome with those problems, the company decided to upgrade its existing systems and integrate a new cloud based integrated system.

Benefits

Star Car Rentals will benefit from the new cloud based integrated system. The proposed system connects different application, system as well as IT environments for real time exchange of the data as well as processes. The system improves connectivity, visibility and optimization of the business operations. This system eliminates existing issues of data duplication as well as manual business work. The system will automate the entire business operations to make it time consuming, faster and efficient. It allows using of cloud applications without installation, access private as well as business files from whichever location throughout a remote internet access. It can improve computing efficiencies by centralization storage, memory as well as processing. It helps to configure of on-premise as well as cloud applications to share of data over cloud. The system is provided up-to-date information related to various business activities. Change into manual segments to automated system improves accuracy of level of business operations such as customer relationship management, vehicle pick up, returns management, accounting, payroll, reservation management and others. The system is also secured as username and password is being allocated to each employee to verify and gain access to the cloud.

From the financial point of view, the implement of new cloud integration system is required of total one-time cost for setting the proposed system is $510,000 with recurring cost per month is $35,000. It is estimated that the company will save an amount of $650,000 per year by means to eliminate lost sales as well as improve operating efficiencies.

Project cost

The one-time cost for setting the systems are:

.Project Phase

Cost

Estimated Elapsed Time in Months

Requirements Analysis

$150,000

2

Configuration and Testing

$200,000

3

User Acceptance Testing

$80,000

3

Implementation including user training

$50,000

2

Setup cost for networking and communication

$30,000

3

Total

$510,000

10

Implement of new Cloud based Integrated System 

Project organization structure 

Following organization structure shows roles of the members those are involved in the project work throughout implementation of new cloud based integrated system in Star Car Rentals.   

Project deliverables

Following are the project deliverables which are provided while implementation of new cloud based integration system in Star Car Rental:

  1. Project charter:It defines statement of objectives in the project. It provides detailed project goals, roles and responsibilities, stakeholder list, level of authority of the project manager, timeline and project cost.
  2. Project management plan:It is an approved document used to manage the project execution work. PMP documents coordinate the planning activities and define the project execution, monitoring, controlling and closing. Each roles and responsibilities of project member is analyzed in this document.
  3. Requirement analysis document:This document provides details on success and failure of the system project. The system is described in terms of functional in addition to non-functional requirements. It serves contractual basis among customer as well as developer.
  4. Budget analysis report:It is a financial plan for defined period of year. It is included with sales volumes, revenue, cost and expenses, liabilities and cash flows. This report provides cost for networking of system across the project lifespan.
  5. Testing and implementation plan:This plan provides details of system features which are required to test, entry and exit criteria. The test cases are written to keep track of the software implemented, and the test analysis report will record results of tests.
  6. Risk management plan:It is a document prepared by the project manager to foresee the project risks, estimate its possible impacts and define the responses to project issues. It provides negative and positive effect on the project objectives.
  7. Lessons learned report:It provides details of learning gained from process to perform the project work. It provides insights of how project processes are to be improved.

Project activities with estimation of person efforts per hours

Resource Name

Work

Project Manager

1,664 hrs

   Preparation of project proposal

16 hrs

   Allocation of requirements among development segments

88 hrs

   Apply lessons learned from earlier projects

24 hrs

   Review to determine readiness to design phase

120 hrs

   Requirement sign off

16 hrs

   Sign off the configuration phase

16 hrs

   Availability of business requirements

216 hrs

   Development of application code

216 hrs

   Regression analysis completion

144 hrs

   Sign off the user acceptance testing

16 hrs

   Sign off the project report

48 hrs

   Project review and closure

64 hrs

   Final project report submission

8 hrs

   Analyze the business requirements

16 hrs

   Revalidate the business needs

80 hrs

   Identify non-functional requirements

120 hrs

   Installation of hardware and software

96 hrs

   Staff training

360 hrs

Business Analyst 01

288 hrs

   Analyze the business requirements

16 hrs

   Identify functional requirements

96 hrs

   Support the build process

96 hrs

   Software configuration

80 hrs

Business Analyst 02

1,176 hrs

   Revalidate the business needs

80 hrs

   Identify functional requirements

96 hrs

   Identify non-functional requirements

120 hrs

   Source code, test scripts

104 hrs

   Third party software and hardware

96 hrs

   Support the build process

96 hrs

   Installation of hardware and software

96 hrs

   Unit, integration and system testing completion

128 hrs

   Staff training

360 hrs

Testers

1,344 hrs

   Source code, test scripts

104 hrs

   Third party software and hardware

96 hrs

   Development and test documentation

80 hrs

   Management of testware and test results

152 hrs

   Support the build process

96 hrs

   Software configuration

80 hrs

   Sign off the configuration phase

16 hrs

   Availability of business requirements

216 hrs

   Development of application code

216 hrs

   Unit, integration and system testing completion

128 hrs

   Regression analysis completion

144 hrs

   Sign off the user acceptance testing

16 hrs

High level project schedule

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

0

Implementation of new cloud based integration system

297 days

Tue 10/9/18

Wed 11/27/19

 

 

1

   Requirements analysis

60 days

Tue 10/9/18

Mon 12/31/18

 

 

1.1

      Preparation of project proposal

2 days

Tue 10/9/18

Wed 10/10/18

 

Project Manager

1.2

      Analyze the business requirements

2 days

Thu 10/11/18

Fri 10/12/18

2

Business Analyst 01 ,Project Manager

1.3

      Revalidate the business needs

10 days

Mon 10/15/18

Fri 10/26/18

3

Business Analyst 02 ,Project Manager

1.4

      Allocation of requirements among development segments

11 days

Mon 10/29/18

Mon 11/12/18

4

Project Manager

1.5

      Apply lessons learned from earlier projects

3 days

Tue 11/13/18

Thu 11/15/18

5

Project Manager

1.6

      Identify potential product and servce providers

27 days

Fri 11/16/18

Mon 12/24/18

 

 

1.6.1

         Identify functional requirements

12 days

Fri 11/16/18

Mon 12/3/18

6

Business Analyst 01 ,Business Analyst 02

1.6.2

         Identify non-functional requirements

15 days

Tue 12/4/18

Mon 12/24/18

8

Business Analyst 02 ,Project Manager

1.7

      Review to determine readiness to design phase

15 days

Fri 11/16/18

Mon 12/31/18

4

Project Manager

1.8

      Requirement sign off

2 days

Tue 12/25/18

Wed 12/26/18

9

Project Manager

2

   Configuration and testing

90 days

Thu 12/27/18

Wed 5/1/19

 

 

2.1

      Determine items make software and system

25 days

Thu 12/27/18

Wed 1/30/19

 

 

2.1.1

         Source code, test scripts

13 days

Thu 12/27/18

Mon 1/14/19

11

Business Analyst 02 ,Testers

2.1.2

         Third party software and hardware

12 days

Tue 1/15/19

Wed 1/30/19

14

Business Analyst 02 ,Testers

2.2

      Development and test documentation

10 days

Thu 1/31/19

Wed 2/13/19

6,15

Testers

2.3

      Management of testware and test results

19 days

Thu 2/14/19

Tue 3/12/19

16

Testers

2.4

      Support the build process

12 days

Wed 3/13/19

Thu 3/28/19

17

Business Analyst 01 ,Business Analyst 02 ,Testers

2.5

      Installation of hardware and software

12 days

Fri 3/29/19

Mon 4/15/19

18

Business Analyst 02 ,Project Manager

2.6

      Software configuration

10 days

Tue 4/16/19

Mon 4/29/19

19

Business Analyst 01 ,Testers

2.7

      Sign off the configuration phase

2 days

Tue 4/30/19

Wed 5/1/19

10,20

Project Manager ,Testers

3

   User acceptance testing

90 days

Thu 5/2/19

Wed 9/4/19

 

 

3.1

      Availability of business requirements

27 days

Thu 5/2/19

Fri 6/7/19

21

Project Manager ,Testers

3.2

      Development of application code

27 days

Mon 6/10/19

Tue 7/16/19

23

Project Manager ,Testers

3.3

      Unit, integration and system testing completion

16 days

Wed 7/17/19

Wed 8/7/19

24

Business Analyst 02 ,Testers

3.4

      Regression analysis completion

18 days

Thu 8/8/19

Mon 9/2/19

25

Project Manager ,Testers

3.5

      Sign off the user acceptance testing

2 days

Tue 9/3/19

Wed 9/4/19

26

Project Manager ,Testers

4

   Implementation including user training

60 days

Thu 9/5/19

Wed 11/27/19

 

 

4.1

      Staff training

45 days

Thu 9/5/19

Wed 11/6/19

27

Business Analyst 02 ,Project Manager

4.2

      Sign off the project report

6 days

Thu 11/7/19

Thu 11/14/19

29

Project Manager

4.3

      Project review and closure

8 days

Fri 11/15/19

Tue 11/26/19

30

Project Manager

4.4

      Final project report submission

1 day

Wed 11/27/19

Wed 11/27/19

31

Project Manager

risk analysis and mitigation  

Type of risk

Description

Probability

Impact

Risk level

Mitigation actions

Organizational risk

Star car rentals have lose over IT governance as well as control in cloud. The company is not carrying out IT auditing over the cloud. Therefore, the cloud provider is failing to support company to meet with its specific industrial regulations.

Unlikely

Moderate

Medium

The company should be careful when making decisions regarding selection of the cloud vendors.  

Operational risk

The cloud provides have not defined Service level agreement among the cloud providers. Therefore, the company has no such capability to meet with established SLA.

Moderate

Moderate

Medium

There should be proper defined service level agreement helps the company to make proper contract between service provider and end user.

Technical risk

Due to various cloud applications, there is data fragmentation as well as data losses. The company has limited control to debug and test application within cloud. Sometimes, there is unauthorized access to the data application.

Likely

Major

High

The company should aware the staffs regarding unauthorized access to confidential information. Two-way password method is used to prevent towards accessing the data from third party access.

Legal risk

The cloud architecture are failed to meet with data privacy as well as protect regulations. Intellectual property issues are raised due to sharing of IT resources over cloud.

Moderate

Major

Medium

The company should implement of strict organizational legal rules so that all confidential data should be kept secured in one place.

Resource risk

The staffs and managers involved in the project are not coordinated and supported to meet with client’s requirements.

Unlikely

Minor

Low

A proper communication plan should be implemented for interaction and coordination purpose. The team members are also encouraged to work effectively for the implementation work.

Quality control 

Plan Quality Management

Quality Assurance

Control Quality

Does the project able to meet with client’s requirements?

Project timeline, budget plan and requirement analysis are ensured if the project meets with its client’s requirements. When the project is delivered on time and the budget is in limit, then the project plan should succeed.

Usage of internal control standards to ensure about quality of timeline and budget.  

Does the project work follow each phases?

Each the project phases are followed and a project schedule assures if all the project phases are followed by the project team members.

Monitoring against the project phases.

Does the system testing properly done?

The system is tested using user acceptance testing to assure if the system would run properly. All the test cases are accurately used for system testing.

User acceptance testing is performed.

Does proper training provided to the staffs regarding new cloud based integrated system implementation?

It ensures if the staffs can get proper training regarding use of system.

Staff training program are conducted in this case.

Does the project documented effectively?

Proper system set up is done to document all the project phases and requirements.

Implementation testing is performed.

Does regular update provided to the project manager?

A project management plan ensures that all the project phases are followed and regular updates are provided to finish the work on scheduled time.

Project management plan documents all project work.

Communication plan 

Project Name: Implementation of Cloud based Integrated System for Star Car Rentals

Prepared by: Project Manager

Position: Project Manager

Date: 28th October, 2018

Version No: v1.0

Document Change Control 

The following is the document control for the revisions to this document.

Version Number

Date of Issue

Author(s)

Brief Description of Change

Version 1.0

28th October, 2018

Project Manager

Initial version for review of project plan

Definition 

The following are definitions of terms, abbreviations and acronyms used in this document.

Term

Definition

ARS

Alpha Rental Software

CRM

Customer Relationship Management

Introduction

The main purpose of this communication plan for Star Car Rentals is providing the stakeholders with information related to the project. The plan defines who should provide information, when the information is delivered and what communication channels used to deliver the information is. The plan is policy driven to provide the stakeholders with the information. This document is primarily for the stakeholders, sets out how Star Car Rentals plans to communicate regarding the implementation of new cloud based integrated system in the business processes. It is included with key group of stakeholders those are required to transfer information to other related to project work. The communication plan accomplishes work with support as well as cooperation with each stakeholder groups. The main goal of communication plan is to maintain control of project as well as ensure that the stakeholders can receive required information. Schedule of weekly project meetings keep the participants updated regarding the project progress. 

Communication Objectives 

The main objectives of communication plan are as follows:

  • Creating awareness among the project team members about the project requirements
  • Creating messages required to maintain public image of the company
  • Determining analysis for each media outlet to reach specific target market
  • Avoiding confusion which affects morale and business productivity
  • Encouraging collaboration in addition to transparency
  • Communicating results of process to broader public audiences
  • Providing timely information and message related to project 
  1. Communication Purpose and Target Audiences

This section provides details regarding the target audiences those are involved in the communication plan along with purpose of communication among the project team members. The below table provides the list of audiences and communication purpose with them.  

Audience

Communication  Purpose

Project Team

Project plan, project update and project issues

Business Analyst

Project specification, business requirements, project deliverables and project direction

Tester

User acceptance testing results and test cases analysis results

Project Sponsor

Project budget and timeline, incorrect project invoices

Communication Message and Delivery

This section provides details on targeted audiences, key messages to the audience, delivery method, frequency for delivery of message and communicator.

Audience

Message

Delivery  Method

Delivery Frequency

Communicator

Project Team

Project plan, Project update Project issues

Business meeting and presentation

Weekly

Project Manager

Business Analyst

Project specification, Business requirements, Project deliverables

Presentation, Email and project report

Weekly

Project Manager

Tester

User acceptance testing results

Business meeting and presentation

Monthly

Project Manager

Project Sponsor

Project budget and timeline

Business meeting and presentation

Weekly

Project Manager

  1. Communication Message Contents

This particular section provides details of message contents of key communication which are performed among targeted audiences such as:

  • Providing update on project findings and development of proposed system
  • Implementation related to next project phases and timeline
  • Business case for project consultation
  • Changes in the business case
  • Executive decisions and project phases
  • Current and future project plan for implementation of proposed system
  • Project status report, summary and status of schedule and budget
  • Goals of the project management plan
  • Project issues and mitigation
  • Project checklist
  • Accomplishment of the project activities

Earned value analysis 

The earned value analysis (EVA) is a method to measure progress of project at given period of time, forecast the completion date, final cost as well as analyze the schedule and budget variance as the project proceeds. It is analyzed by calculating three main elements:

  1. Planned value (PV)- It is first element of the earned value management. It is value of work to complete at provided time. It is authorized budget assigned to project work for accomplishment of an activity or component of WBS.

Earned value (PV) = planned % completed work * budget at completion

  1. Actual cost (AC)- It is second element of the earned value management. It is total cost incurred for actual work complete to date. It is total cost incurred in accomplishment of work performed for an activity or component of WBS.

Actual cost (AC) = hourly rate* total hours spent

  1. Earned value (EV)- It is third element of the earned value management. It is the value of work completed to date. It is the value of work performed in terms of budget assigned to work of an activity or component of WBS.

Earned value (EV) = % completed work * budget at completion  

Budgeted Cost of Work Schedule/Planned Value:

 

 

 

Project Manager

Business Analyst 1

Tester

Particulars

Cost

Estimated Elapsed Time

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

 

 

 

 

 

 

 

 

 

 

 

 

Requirements Analysis

$150,000

2

2

$135

$56,160

2

$110

$45,760

 

$80

 

Configuration & Testing

$200,000

3

3

$135

$84,240

2

$110

$45,760

 

$80

$0

User Acceptance Testing

$80,000

3

3

$135

$84,240

1

$110

$22,880

6

$80

$99,840

Implementation including user training

$50,000

2

2

$135

$56,160

4

$110

$91,520

 

$80

$0

Setup Cost for networking & communication

$30,000

 

0

$135

$0

0

$110

$0

 

$80

$0

TOTAL

$510,000

10

10

$135

$280,800

9

$110

$205,920

6

$80

$99,840

 

Budgeted Cost of Work Performance / Earned Value:

 

 

 

 

Project Manager

Business Analyst 1

Tester

Particulars

% of Completion

Cost

Estimated Elapsed Time

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

Requirements Analysis

100%

$150,000

2

2

$135

$56,160

2

$110

$45,760

0

$80

$0

Configuration & Testing

80%

$160,000

2.4

2.4

$135

$67,392

1.6

$110

$36,608

0

$80

$0

User Acceptance Testing

0%

$0

0

0

$135

$0

0

$110

$0

0

$80

$0

Implementation including user training

0%

$0

0

0

$135

$0

0

$110

$0

0

$80

$0

Setup Cost for networking & communication

80%

$24,000

 

0

$135

$0

0

$110

$0

0

$80

$0

TOTAL

 

$334,000

4.4

4.4

$135

$123,552

3.6

$110

$82,368

0

$80

$0

 

 

 

Actual Cost of Work Performance/ Actual Cost:

 

 

 

 

Project Manager

Business Analyst 1

Tester

Particulars

% of Completion

Cost

Estimated Elapsed Time

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

Requirements Analysis

100%

$157,500

2

2

$135

$56,160

2

$110

$45,760

0

$80

$0

Configuration & Testing

80%

$168,000

2

2

$135

$56,160

4

$110

$91,520

0

$80

$0

User Acceptance Testing

0%

$0

0

0

$135

$0

0

$110

$0

0

$80

$0

Implementation including user training

0%

$0

0

0

$135

$0

0

$110

$0

0

$80

$0

Setup Cost for networking & communication

80%

$24,000

 

0

$135

$0

0

$110

$0

0

$80

$0

TOTAL

 

$349,500

4

4

$135

$112,320

6

$110

$137,280

0

$80

$0

 

Estimates at Completion:

 

 

 

 

Project Manager

Business Analyst 1

Tester

Particulars

% of Completion

Cost

Estimated Elapsed Time

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

Estimated Effort

Cost per hour

Labor Cost

 

 

 

 

 

 

 

 

 

 

 

 

 

Requirements Analysis

0%

$4,500

0

0

$135

$0

0

$110

$0

0

$80

$0

Configuration & Testing

20%

$49,200

1

1

$135

$28,080

2

$110

$45,760

0

$80

$0

User Acceptance Testing

100%

$80,000

3

2

$135

$56,160

1

$110

$22,880

6

$80

$99,840

 

 

 

 

1

$140

$29,120

 

 

 

 

 

 

Implementation including user training

100%

$50,000

2

2

$140

$58,240

4

$110

$91,520

0

$80

$0

Setup Cost for networking & communication

20%

$6,000

 

0

$140

$0

0

$110

$0

0

$80

$0

TOTAL

 

$189,700

6

6

$140

$171,600

7

$110

$160,160

6

$80

$99,840

In order to estimate Earned value analysis, following terms are used and its respective formulas such as:

  1. Cost variance (CV) -It is difference between cost of actual amount and budgeted or planned amount.  It is completed work cost as compared to planned cost. Therefore, it is difference between earned value and actual cost.

CV= EV-AC

When there is positive cost variance, then the project is under budget and when there is negative cost variance, then the project is over budget. 

  1. Budget at Completion (BAC)- It is total budget allocated to project work. It is plotted over the project time.

BAC = Baseline Effort-hours * Hourly Rate  

  1. Estimate at Completion (EAC) – It is calculated by dividing budget at completion by the cost performance index.

EAC = Budget at completion / cost performance index

Following table shows the earned value analysis for the project work:

Earned Value Analysis:

 

 

 

 

 

 

Labor Cost

Particulars

Total Cost

Project Manager

Business Analyst

Tester

 

 

 

 

 

Actual Cost

$349,500

$112,320

$137,280

$0

Budget at Completion

$510,000

$280,800

$205,920

$99,840

Earned Value

-$334,000

-$123,552

-$82,368

$0

Estimate at Completion

$525,500

$269,568

$260,832

$99,840

 

 

 

 

 

Actual Cost

$349,500

$112,320

$137,280

$0

New Estimates

$189,700

$171,600

$160,160

$99,840

New Estimate at Completion

$539,200

$283,920

$297,440

$99,840

 

 

 

 

 

Variance

-$13,700

-$14,352

-$36,608

$0

It is analyzed that the cost variance of this project is negative; therefore the project is over budget. There is an increase in cost as compared to actual cost and planned cost.   

Conclusion

It is concluded that the cloud system implementation plan is consisted of various benefits in the business process of company so that there is increase in market share, increase in business productivity. Therefore, the business is benefited due to implementation and received positive project outcome. The project activities are followed of proper schedule to finish the work on scheduled time. After analyzing earned value analysis, it is estimated that there is negative cost variance; therefore the project plan is over budgeted. Communication plan helps the project stakeholders to interact and cooperate with each other to make a successful project plan. Risk management plan determines the project risks which are occurred due to implementation of proposed system in cloud computing environment. Mitigation steps are also taken to make the project risk free so that there is no possibility of project failure within scheduled time as well as budget. Quality is also analyzed for the project to deliver quality products and services to client for meeting with the business requirements. 

Bibliography

[1] Kerzner, H. and Kerzner, H.R.. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons, 2017.

[2] Turner, J.R. Handbook of project-based management (Vol. 92). New York, NY: McGraw-hill, 2014.

[3] Larson, E.W. and Gray, C.F. A Guide to the Project Management Body of Knowledge: PMBOK (®) Guide. Project Management Institute, 2015.

[4] Binder, J. Global project management: communication, collaboration and management across borders. Routledge, 2016.

[5] Hornstein, H.A. The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), pp.291-298, 2015.

[6] Joslin, R. and Müller, R. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392, 2015.

[7] Muller, R.,. Project governance. Routledge, 2017

[8] Karaman, E. and Kurt, M. Comparison of project management methodologies: prince 2 versus PMBOK for it projects. Int. Journal of Applied Sciences and Engineering Research, 4(5), pp.657-664, 2015.

[9] Saltz, J., Hotz, N., Wild, D. and Stirling, K. Exploring Project Management Methodologies Used Within Data Science Teams, 2018

[10] Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P. Project risk management methodology for small firms. International journal of project management, 32(2), pp.327-340, 2014.

[11] Harrison, F. and Lock, D. Advanced project management: a structured approach. Routledge, 2017. 

[12] Marchewka, J.T.. Information technology project management. John Wiley & Sons, 2014.

[13] Martens, M.L. and Carvalho, M.M. The challenge of introducing sustainability into project management function: multiple-case studies. Journal of Cleaner Production, 117, pp.29-40, 2016.

[15] Kerzner, H. Project management 2.0: leveraging tools, distributed collaboration, and metrics for project success. John Wiley & Sons, 2015.

[16] Leach, L.P., 2014. Critical chain project management. Artech House, 2014.

[17] Kendrick, T. Identifying and managing project risk: essential tools for failure-proofing your project. Amacom, 2015.

[18] Bourne, L. Stakeholder relationship management: a maturity model for organisational implementation. Routledge, 2016.

[19] Newton, R. Project management step by step: how to plan and manage a highly successful project. Pearson UK, 2016.

[20] Ramazani, J. and Jergeas, G. Project managers and the journey from good to great: The benefits of investment in project management training and education. International Journal of Project Management, 33(1), pp.41-52, 2015.


Buy Iscg8022 Managing Information Technology Projects Assessment Answers Online


Talk to our expert to get the help with Iscg8022 Managing Information Technology Projects Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Iscg8022 Managing Information Technology Projects Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.