You can select one of the two following case studies or create one of your own. If you create one of your own add the case study to the assignment submission.
Case One Information Systems
The assignment one project is to develop a project estimating, costing and budgeting system. The system is a bespoke system and can be written in a programming language of your choice e.g C#.The system must be able to create a cost baseline, cash flow forecast, earned value management calculations and percentage complete proposal. The system will be able to have data entered, data imported via comma delimited files or XML.It is necessary to purchase a server to run the system and 25 client PCs. The PCs need to be configured with Windows 10 and added to an existing network. The server needs to be setup and tested.

Subcontractors will be required to develop the software The project requires at a minimum the high-level work activities as follows.
? requirements gathering
? technical specification
? development
 
The above elements need to be expanded to create a project plan Case Two Environmental Science You are required to undertake research to try to ascertain if the Great Barrier Reef is being damaged by global warming on phosphates. You will need to conduct research that has three environments, a placebo environment, a warm water environment and a phosphates environment. This will require obtaining coral,setting up tanks to contain the coral and undertaking the research.It is necessary to purchase tanks and ancillary equipments such as heaters and phospherates. A boat will
need to be chartered. The coral will need to be monitored over a six week period. The Queensland governmet will pay for the project. Three researchers will be required to run the project as well as lab.

technicians as required and contractors to build the tanks.The project requires at a minimum the high-level work activities as follows.acceptance by Queeensland government The above elements need to be expanded to create a project plan

Answer:

The project of System development (Bespoke System) for cost management activities has been developed using the information technology management for the development of the successful and integrated management process. The information system developed (bespoke system) would be helpful for ensuring the completion of the cost benefit analysis and integrating the management of the successful integration management. The successful analysis of the factors would be capable of integrating the operation development for the complete integration and development.

The project has been initiated by the Consultancy Firm for developing the system for their cost management activities. David James was the CEO of the consultancy firm and the primary owner of the project. The CEO of State Bank, Barney Lewis would serve the project requirement analysis. The project team members and end users of the system are the other stakeholders of the project.

1.2 Problem Statement

The organization had required the faster and more effective management of the activities for ensuring the deployment of the innovative operations. The significant utilization of the factors would be helpful for ensuring the management of the factors and integration management. The major problem is faced when the effective cost factors, management plan, and resource management would be required. The problem definition is helpful for identifying the prospect of issues identification for the project.

1.3 Project Deliverables

The deliverables of the project of System development (Bespoke System) for cost management activities include,

  • Project Documents (initiation, planning, and final reports)
  • System Design and Program for the system
  • Merged Server (existing with the new server)
  • Client PC configuration with Windows 10
  • .4 Milestones

The milestones for the project of System development (Bespoke System) for cost management activities includes,

WBS

Task Name

Duration

Start

Finish

M1

Project is kicked off

0 days

Thu 10/11/18

Thu 10/11/18

M2

Resources are accumulated

0 days

Wed 10/10/18

Wed 10/10/18

M3

   Design is developed

0 days

Fri 10/12/18

Fri 10/12/18

M4

   System is developed

0 days

Wed 10/17/18

Wed 10/17/18

M5

Configuration of PCs is done

0 days

Thu 10/25/18

Thu 10/25/18

M6

Results are documented

0 days

Mon 10/29/18

Mon 10/29/18

M7

Training Completed

0 days

Thu 10/25/18

Thu 10/25/18

M8

Project is closed

0 days

Fri 11/2/18

Fri 11/2/18

The cost estimates for the project of System development (Bespoke System) for cost management activities,  

Resource Name

Type

Work

Standard Rate

Cost

Project Manager

Work

40

$100.00

$4,000.00

Planner

Work

32

$40.00

$1,280.00

Network Engineer

Work

88

$90.00

$7,920.00

Data Admin

Work

64

$75.00

$4,800.00

Programmer

Work

96

$90.00

$8,640.00

Designer

Work

16

$70.00

$1,120.00

System Engineer

Work

56

$95.00

$5,320.00

Tester

Work

64

$60.00

$3,840.00

Trainer

Work

64

$50.00

$3,200.00

Support team

Work

48

$45.00

$2,160.00

Server Cost

Human

1

$2,000.00

$2,000.00

Design Software

Human

1

$1,000.00

$1,000.00

Database Storage

Human

1

$1,000.00

$1,000.00

Programming Software

Human

1

$1,300.00

$1,300.00

Windows 10

Human

10

$100.00

$1,000.00

NIC Card

Human

10

$50.00

$500.00

Testing tools

Human

4

$200.00

$800.00

Documents

Human

3

$40.00

$120.00

Total Budget

$50,000.00

The assumptions of the project of System development (Bespoke System) for cost management activities are,

  • Completion of project in estimated time and budget
  • Feasible Project plan is made
  • Positive Test Results are found
  • Implementation plan is helpful for successful operations

The risks for the project of System development (Bespoke System) for cost management activities are,

Risk

Likelihood (L)

Impact (I)

Rating (L*I)

Delay in Completion

5

2

10

Over budget

3

3

9

Issues in Server Installation

2

5

10

Compiling Errors in Codes

3

5

15

Installation Issues

2

4

8

The limitations of the project of System development (Bespoke System) for cost management activities are,

  • Time bounded by 25 days
  • Budget Bounded by $50,000.00
  • Quality Constraint of automatic cost estimation

The acceptance criteria of System development (Bespoke System) for cost management activities are,

  • Project completed in time
  • No Extra resources have been used
  • System is helpful for generating automatic cost estimation 
 
Procurement Plan

The procurement plan of operations had been developed for entitling the improvement of the factors and listing effective contract between the contracts in the project with project owner. The procurement plan would be effectively dealt with the management of the activities. The completion of the project would be effectively managed with the development plan.

Communication Plan

The communication operation has been helpful for development of the factors aligning the utilization and development. The communication plan would be helpful for taking care of the information transfer and listing proper management of the successive management. The improved information transfer would be helpful for making sure that the information access can be aligned effectively.

Budget Cost Estimates

Resource Name

Type

Work

Standard Rate

Cost

Project Manager

Work

40

$100.00

$4,000.00

Planner

Work

32

$40.00

$1,280.00

Network Engineer

Work

88

$90.00

$7,920.00

Data Admin

Work

64

$75.00

$4,800.00

Programmer

Work

96

$90.00

$8,640.00

Designer

Work

16

$70.00

$1,120.00

System Engineer

Work

56

$95.00

$5,320.00

Tester

Work

64

$60.00

$3,840.00

Trainer

Work

64

$50.00

$3,200.00

Support team

Work

48

$45.00

$2,160.00

Server Cost

Human

1

$2,000.00

$2,000.00

Design Software

Human

1

$1,000.00

$1,000.00

Database Storage

Human

1

$1,000.00

$1,000.00

Programming Software

Human

1

$1,300.00

$1,300.00

Windows 10

Human

10

$100.00

$1,000.00

NIC Card

Human

10

$50.00

$500.00

Testing tools

Human

4

$200.00

$800.00

Documents

Human

3

$40.00

$120.00

Total Budget

$50,000.00

17 Parametric/Bottom up

The parametric estimation of the cost is done by using effective bottom up estimation in which the project resources are aligned cohesively for ensuring the management of the factors for development and alignment of the improved resources. The bottom up estimation is done by considering the factors of information management development. The analysis of the factors and significant utilization of the operations had resulted in forming major setback for the integration and development of effective estimation of the costs. The bottom up estimation is helpful for taking care of the resource utilization and analysis of the successful estimation process.

2. Stakeholder Register

The stakeholder register for the project of Development of Bespoke System for project estimating, costing, and budgeting system are,

Name

Position

Role

Contact Information

Requirements

Expectations

Influence

Classification

David James

CEO of Consultancy Firm

Owner

+41-XXXX-XXXX

Bespoke System

High

High

Internal

Barney Lewis

CEO of State Bank

Sponsor

+41-XXXX-XXXX

Revenue Generation

High

High

External

<<name of the student>>

Manager of the Project Firm

Project Manager

+41-XXXX-XXXX

Completion of project

Low

High

Internal

Barry Simpson

Head Engineer

Programmer

+41-XXXX-XXXX

Execution of the codes

Low

Low

External

Ross Bing

Quality Head

Analyst

+41-XXXX-XXXX

Functions of the System

High

Low

External

Bibliography

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.

Heagney, J. (2016). Fundamentals of project management. Amacom.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Kerzner, H. (2018). Project management best practices: Achieving global excellence. John Wiley & Sons.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.


Buy Man6925 The Project Of System Assessment Answers Online


Talk to our expert to get the help with Man6925 The Project Of System Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Man6925 The Project Of System Assessment Answers Assignment Help Online


); }
Copyright © 2009-2023 UrgentHomework.com, All right reserved.