AM804001 The Roles and Importance of Project Management

This assignment builds on the project charter. The project management plan is the core of the project. It is the integrated framework which includes the management plans from all of the project management knowledge areas. It ties these management plans together into a collective whole which is then used to manage the project through to completion.

The project plan is a detailed document and as such your assessment should provide enough detailed planning to complete the proposed project, it will also provide some academic grounding.

As an individual, you will produce a project management plan, from one of the scenarios given in assessment 1. You may either build on your existing charter, or choose to develop a different project scenario from the same list as follows:

  1. The addition of a garden and BBQ area on the roof of the OPAIC building for staff and summer functions, including the ability to serve beverages and accommodate crowds of up to 80. The area needs to accommodate ‘green building’ principles and take no longer than 6 months to completion.
  2. A new website for the OPAIC Industry Internship Students, including pages to guide students on course material, CV build, interview techniques, how to complete their internship project, potential intern search of both candidates and organisations and advertising from potential internship companies, and a messaging system with appropriate security for each level of user.
  3. A 2-day OPAIC event including workshops and information sessions bringing together potential industry interns with prospective companies, including internship options, graduates speaking about their internships, food and key industry speakers from internship companies, to be held in the Aotea centre. Followed by an after dark networking session on the first day.
  4. Renovating the 8th floor of OPAIC into a full library space that incorporates modern ways to study, including collaborative work spaces, informal seating, technology, and self-checkout capabilities for course text.

N.B. Whilst this plan builds on the charter document, there is an expectation that no more than 10% of the charter will be copied across to the plan, and where this occurs you will reference your charter. More of the charter document copied through will occur plagiarism penalties as described in the course outline.

Answer:

 This report depicts the roles and importance of project management mechanism in industrial manufacturing. Effective and structured project management can reduce the risks assure the quality of a project by ensuring the completion of project within estimated budget and time. The rate of errors can be prevented and at the same time the project budget can be controlled with regulatory and voluntary regulations. For this specific report the nominated project is “The Addition of a Garden and BBQ Area on the Roof of the OPAIC Building”. It is the role of the project manager and other project team members to complete the project within 6 months and estimated budget of $75,000.

In order to accomplish the project successfully measureable components those are to be calculated and considered include project management approach, scope measuring the milestones and management strategies. In addition to this, change management plan, communication management, risk management and project approval requirements are to the other factors that should be outlines at the project initiation phase. A cost baseline, quality baseline, procurement management plan and project schedule are developed by the project team members. The final project charter should be approved by the sponsor and the project manager.

2. Project management approach

Project management tools and techniques will be considered by the project manager to design the work package with duration and cost details. For reducing the workload from the project team members, skilled and experienced project resources will be nominated and allotted for specific project activities. The aim of the project is to build an additional garden and BBQ area on the roof top of the OPAIC building mainly for the summer functions arranged for the staffs of the company. The functions will be arranged in the BBQ areas should serve beverages and must have ability to offer accommodations for 80 staffs.

In order to reduce trash, pollution and environmental degradation the principle of Green building for protecting the health of the occupants are being used by the project manager. It will improve the overall productivity of the project with environmental, economical and social profit. The operating cost for the BBQ area will be diminished, the strain on the local infrastructure will be reduced. The quality of surrounding air and water will be improved accordingly. With the effective consumption of energy from biodiversity the ecosystem will be protected.

3. Project scope including milestones and management plan

The scope for this specific project is to develop additional garden area for the staffs associated to the OPAIC Company. This additional garden area will build at the roof top of the company if any functions are being arranged by the company itself. The designer should keep in mind that the accommodation for the functions will be arranged for around 80 staffs. The designer will consider the concept and principle of Green Building while developing the building. It is expected that for the successful accomplishment of the project will not take longer than 6 months. Maximum rate of success can be obtained from the green building with new technologies. It will create such a green structure that will be beneficial for the economical and social success of the company. The green construction can integrate the economical and social factors all together.

For this specific project on “Addition of garden and BBQ area in the roof top of OPAIC Company” mainly arranged for the summer functions and staff programs the fie main phases those will be considered include project initiation, project planning, development, monitoring and control and project closure. It is necessary for the project manager to follow all these phases accordingly so that within 6 months the project can be successfully accomplished. The milestones and planning details are elaborated in this report below:

Milestone 1: Completion of project initiation phase

0 days

Tue 8/21/18

Tue 8/21/18

25

business analyst

Milestone 2: Completion of project planning phase

0 days

Mon 12/17/18

Mon 12/17/18

66

sponsors

Milestone 3: Completion of project development phase

0 days

Fri 3/1/19

Fri 3/1/19

80

HR manager

Milestone 4: Completion of project monitoring and control phase

0 days

Mon 3/18/19

Mon 3/18/19

94

business analyst

Milestone 5: Completion of project closure phase

0 days

Fri 3/29/19

Fri 3/29/19

106

operation manager

4. Schedule baseline and work break down structure (WBS)

Schedule baseline is referred to as an approved version of schedule model which can be changed accordingly with the changed taking place in the control process of the project. It is also used to make comparison between the planned and actual cost and schedule results. It is possible for any project that it contains contingency reservations which causes time buffer and cost buffer as well. In order to avoid this kind of schedule uncertainty proper schedule baseline and work break down structure is needed to be prepared by the project manager and project team members as well.

If the project scope and assumption changes then respectively the schedule baseline will also change. The duration of different activities must be set based on its complexity. For successful accomplishment of the BBQ garden area project documents such as schedule performance measures, start dates, finish dates, additional works and omitted works all are to be defined with professional perfection. If new works are added by the project head then the changes will also be reflected on the schedule baseline. The components those will be considered for this specific project are as follows:

Baseline: Usually at the initiation point of the BBQ garden area project the project baseline will be set to avoid further financial errors.

Cost and scope baseline: In order to obtain maximum satisfactory result for the consumers the project management includes different responsibilities for the project manager and the team members as well.

Performance maintenance baseline: In regards of the project management area proper determination of the project resources, cost and time are very much necessary to prevent unwanted activities or project actions.

Baseline finish date: The baseline finish dates are activated on those dates only on which that particular activity is expected to be completed on successfully.

In order to reduce the workload from the project team members and to make the project less complex this large BBQ garden area development project should be divided into small sub-activities. For each of those activities different skillful and experienced human resources will be allocated and it will be their responsibilities to complete that specific activity on that specified time period without any error. The Work Breakdown Structure requires active participation from the project team members and is comprise of three basic steps:

  • Proper identification of the specific project deliverables
  • Segmentation of these activities into proper sub project activities
  • Determining proper match between the project resources and their work packages

WBS

Task Name

Ranking

0

schedule for Addition of garden and BBQ area

 

1

Project initiation phase

 

1.1

Understanding project details

High

1.2

Developing project SMART goal

High

1.3

Site analysis of OPAIC building

High

1.4

Creating project assumptions

High

1.5

Identifying project milestone

High

1.6

Describing project purpose to the project sponsors

High

1.7

Requirements gathering

High

1.8

Requirements specifications

High

1.9

Requirements analysis

Medium

1.10

Project description with boundary and limitation analysis

Medium

1.11

High level functional and non-functional project requirements

Medium

1.12

Project description and boundaries

Medium

1.13

Project assumptions and triple project constraints

Medium

1.14

Summary milestones

Medium

1.15

Project risks and risk register

Medium

1.16

Budget summary

High

1.17

Project stakeholders and resource management details

High

1.18

High level functional and non-functional project requirements

High

1.19

Project description and boundaries

High

1.20

Project assumptions and triple project constraints

High

1.21

Summary milestones identification

High

1.22

Feasibility analysis

High

1.23

Interview for the project team

High

1.24

Project team development

High

1.25

Milestone 1: Completion of project initiation phase

 

2

Project planning phase

 

2.1

Research

 

2.1.1

Details market research

High

2.1.2

Acquisition of project vendors

Low

2.1.3

Probability plan for consumer base

Low

2.1.4

Interior design planning

Medium

2.1.5

Exterior design planning

Medium

2.1.6

Site proposal for OPAIC plan

Medium

2.1.7

Food menu planning

Medium

2.2

Project procurement planning

 

2.2.1

OPAIC building area/location acquisition

Low

2.2.2

Permit for the business registry

Low

2.2.3

Kitchen equipments

Low

2.2.4

Renovation materials adoption

Low

2.3

Project renovation planning

 

2.3.1

BBQ area demolition

High

2.3.2

Garden and BBQ area construction

High

2.3.3

Repairing and construction faults

High

2.3.4

Installation of equipments

High

2.3.5

Janitorial requirements analysis

High

2.3.6

Onsite freezers

High

2.4

Advertisement for the BBQ area

 

2.4.1

Radio and television

Medium

2.4.2

News papers and telephone calls

Medium

2.4.3

Posters and banners

Low

2.5

Project staffing

 

2.5.1

Personnel acquisition

Low

2.5.2

Employee on job training classes

Medium

2.5.3

Workshop arrangements

Medium

2.5.4

Adopting training materials

Low

2.5.5

Work schedule development

Low

2.5.6

Janitorial staffing for the project

Low

2.6

Project planning details

 

2.6.1

Risk management plan

Medium

2.6.2

Contingency planning

Medium

2.6.3

Communication program development

Medium

2.6.4

Budget and time management plan

High

2.6.5

Change management plan

High

2.6.6

Technology implementation planning

High

2.6.7

Incorporating green building principles

High

2.6.8

Milestone 2: Completion of project planning phase

 

3

Development phase

 

3.1

Green building Technology concept implementation

Medium

3.2

Technology simulation

Medium

3.3

Originating requirements implementation

Medium

3.4

Functional requirements implementation

Medium

3.5

Performance requirements implementation

Low

3.6

Derived requirements implementation

Low

3.7

Energy trends implementation

Low

3.8

Trade off analysis

Low

3.9

Technology renew

High

3.10

Catering service contract

High

3.11

Electricity contract

High

3.12

Other strategic planning

High

3.13

Milestone 3: Completion of project development phase

 

4

Project control and monitoring phase

 

4.1

Building inventory

High

4.2

Developing training programs

High

4.3

Energy consumption ideas

High

4.4

Energy consumption strategies

High

4.5

Cost analysis based on Green building

High

4.6

Energy profile per square foot

High

4.7

Green technology strategic approach

High

4.8

Green technology tactical approach

Low

4.9

Surveillance camera setting

Low

4.10

Accommodation development for 80 staffs for OPAIC building

Low

4.11

Space efficiency analysis

Low

4.12

ROI analysis

Low

4.13

Milestone 4: Completion of project monitoring and control phase

 

5

Project closure phase

Low

5.1

Operation testing

High

5.2

Stocking

High

5.3

Project flow and timing details

High

5.4

Resupply scheduling

High

5.5

Grand opening planning for the business

High

5.6

Verification

Low

5.7

Validation

High

5.8

Post project maintenance plan

Low

5.9

Project approval requirements

High

5.10

Project approval documentation

Low

5.11

Milestone 5: Completion of project closure phase

 

Key resources (time and cost against work packages)

Resource Name

Std. Rate

Responsibility

project manager

$55.00/hr

To complete the project within estimated cost and time

finance manager

$40.00/hr

To estimate the accurate project budget

interior designer

$50.00/hr

To make the BBQ area attractive to the customers or staffs of OPAIC

caterers

$38.00/hr

To serve quality and unique food items

HR manager

$30.00/hr

To manage the employees

sponsors

$65.00/hr

To invest proper capital

technical head

$45.00/hr

Ti incorporate technical Green building principles

operation manager

$45.00/hr

To make the business operation feasible

technical team

$32.00/hr

To develop technical structure

business analyst

$48.00/hr

To give market success and competitive advantages

5. Project plan list of schedule items/activities

The entire project will take 6 months for successful completion with an estimated budget rate of $72,730.00.

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

0

schedule for Addition of garden and BBQ area

180 days

Mon 7/23/18

Fri 3/29/19

$72,728.00

1

Project initiation phase

22 days

Mon 7/23/18

Tue 8/21/18

$9,232.00

1.1

Understanding project details

1 day

Mon 7/23/18

Mon 7/23/18

project manager

$440.00

1.2

Developing project SMART goal

1 day

Tue 7/24/18

Tue 7/24/18

2

finance manager

$320.00

1.3

Site analysis of OPAIC building

1 day

Wed 7/25/18

Wed 7/25/18

3

interior designer

$400.00

1.4

Creating project assumptions

2 days

Wed 7/25/18

Thu 7/26/18

3

caterers

$608.00

1.5

Identifying project milestone

2 days

Thu 7/26/18

Fri 7/27/18

4

HR manager

$480.00

1.6

Describing project purpose to the project sponsors

1 day

Mon 7/30/18

Mon 7/30/18

5,6

sponsors

$520.00

1.7

Requirements gathering

1 day

Tue 7/31/18

Tue 7/31/18

7

technical head

$360.00

1.8

Requirements specifications

1 day

Wed 8/1/18

Wed 8/1/18

8

operation manager

$360.00

1.9

Requirements analysis

1 day

Thu 8/2/18

Thu 8/2/18

9

technical team

$256.00

1.10

Project description with boundary and limitation analysis

1 day

Fri 8/3/18

Fri 8/3/18

10

business analyst

$384.00

1.11

High level functional and non-functional project requirements

1 day

Mon 8/6/18

Mon 8/6/18

11

interior designer

$400.00

1.12

Project description and boundaries

1 day

Mon 8/6/18

Mon 8/6/18

11

caterers

$304.00

1.13

Project assumptions and triple project constraints

1 day

Tue 8/7/18

Tue 8/7/18

12,13

HR manager

$240.00

1.14

Summary milestones

1 day

Wed 8/8/18

Wed 8/8/18

14

sponsors

$520.00

1.15

Project risks and risk register

1 day

Thu 8/9/18

Thu 8/9/18

15

sponsors

$520.00

1.16

Budget summary

1 day

Fri 8/10/18

Fri 8/10/18

16

technical head

$360.00

1.17

Project stakeholders and resource management details

1 day

Mon 8/13/18

Mon 8/13/18

17

operation manager

$360.00

1.18

High level functional and non-functional project requirements

1 day

Tue 8/14/18

Tue 8/14/18

18

technical team

$256.00

1.19

Project description and boundaries

1 day

Wed 8/15/18

Wed 8/15/18

19

business analyst

$384.00

1.20

Project assumptions and triple project constraints

1 day

Thu 8/16/18

Thu 8/16/18

20

technical head

$360.00

1.21

Summary milestones identification

1 day

Thu 8/16/18

Thu 8/16/18

20

operation manager

$360.00

1.22

Feasibility analysis

1 day

Fri 8/17/18

Fri 8/17/18

21,22

technical team

$256.00

1.23

Interview for the project team

1 day

Mon 8/20/18

Mon 8/20/18

23

business analyst

$384.00

1.24

Project team development

1 day

Tue 8/21/18

Tue 8/21/18

24

interior designer

$400.00

1.25

Milestone 1: Completion of project initiation phase

0 days

Tue 8/21/18

Tue 8/21/18

25

business analyst

$0.00

2

Project planning phase

84 days

Wed 8/22/18

Mon 12/17/18

$34,768.00

2.1

Research

33 days

Wed 8/22/18

Fri 10/5/18

$13,272.00

2.1.1

Details market research

9 days

Wed 8/22/18

Mon 9/3/18

26

project manager

$3,960.00

2.1.2

Acquisition of project vendors

5 days

Tue 9/4/18

Mon 9/10/18

29

finance manager

$1,600.00

2.1.3

Probability plan for consumer base

2 days

Tue 9/11/18

Wed 9/12/18

30

interior designer

$800.00

2.1.4

Interior design planning

3 days

Thu 9/13/18

Mon 9/17/18

31

caterers

$912.00

2.1.5

Exterior design planning

5 days

Tue 9/18/18

Mon 9/24/18

32

HR manager

$1,200.00

2.1.6

Site proposal for OPAIC plan

3 days

Tue 9/18/18

Thu 9/20/18

32

sponsors

$1,560.00

2.1.7

Food menu planning

9 days

Tue 9/25/18

Fri 10/5/18

33,34

technical head

$3,240.00

2.2

Project procurement planning

20 days

Mon 10/8/18

Fri 11/2/18

$7,008.00

2.2.1

OPAIC building area/location acquisition

1 day

Mon 10/8/18

Mon 10/8/18

35

technical team

$256.00

2.2.2

Permit for the business registry

5 days

Tue 10/9/18

Mon 10/15/18

37

business analyst

$1,920.00

2.2.3

Kitchen equipments

6 days

Tue 10/16/18

Tue 10/23/18

38

interior designer

$2,400.00

2.2.4

Renovation materials adoption

8 days

Wed 10/24/18

Fri 11/2/18

39

caterers

$2,432.00

2.3

Project renovation planning

15 days

Mon 11/5/18

Fri 11/23/18

$6,360.00

2.3.1

BBQ area demolition

5 days

Mon 11/5/18

Fri 11/9/18

40

sponsors

$2,600.00

2.3.2

Garden and BBQ area construction

2 days

Mon 11/12/18

Tue 11/13/18

42

sponsors

$1,040.00

2.3.3

Repairing and construction faults

2 days

Wed 11/14/18

Thu 11/15/18

43

technical head

$720.00

2.3.4

Installation of equipments

2 days

Fri 11/16/18

Mon 11/19/18

44

operation manager

$720.00

2.3.5

Janitorial requirements analysis

2 days

Tue 11/20/18

Wed 11/21/18

45

technical team

$512.00

2.3.6

Onsite freezers

2 days

Thu 11/22/18

Fri 11/23/18

46

business analyst

$768.00

2.4

Advertisement for the BBQ area

5 days

Mon 11/26/18

Fri 11/30/18

technical head

$3,440.00

2.4.1

Radio and television

1 day

Mon 11/26/18

Mon 11/26/18

47

operation manager

$360.00

2.4.2

News papers and telephone calls

2 days

Tue 11/27/18

Wed 11/28/18

49

technical team

$512.00

2.4.3

Posters and banners

2 days

Thu 11/29/18

Fri 11/30/18

50

business analyst

$768.00

2.5

Project staffing

5 days

Mon 12/3/18

Fri 12/7/18

$2,224.00

2.5.1

Personnel acquisition

1 day

Mon 12/3/18

Mon 12/3/18

51

project manager

$440.00

2.5.2

Employee on job training classes

1 day

Tue 12/4/18

Tue 12/4/18

53

finance manager

$320.00

2.5.3

Workshop arrangements

1 day

Wed 12/5/18

Wed 12/5/18

54

interior designer

$400.00

2.5.4

Adopting training materials

1 day

Wed 12/5/18

Wed 12/5/18

54

caterers

$304.00

2.5.5

Work schedule development

1 day

Thu 12/6/18

Thu 12/6/18

55,56

HR manager

$240.00

2.5.6

Janitorial staffing for the project

1 day

Fri 12/7/18

Fri 12/7/18

57

sponsors

$520.00

2.6

Project planning details

6 days

Mon 12/10/18

Mon 12/17/18

$2,464.00

2.6.1

Risk management plan

1 day

Mon 12/10/18

Mon 12/10/18

58

operation manager

$360.00

2.6.2

Contingency planning

1 day

Tue 12/11/18

Tue 12/11/18

60

technical team

$256.00

2.6.3

Communication program development

1 day

Wed 12/12/18

Wed 12/12/18

61

business analyst

$384.00

2.6.4

Budget and time management plan

1 day

Wed 12/12/18

Wed 12/12/18

61

interior designer

$400.00

2.6.5

Change management plan

1 day

Thu 12/13/18

Thu 12/13/18

62,63

caterers

$304.00

2.6.6

Technology implementation planning

1 day

Fri 12/14/18

Fri 12/14/18

64

HR manager

$240.00

2.6.7

Incorporating green building principles

1 day

Mon 12/17/18

Mon 12/17/18

65

sponsors

$520.00

2.6.8

Milestone 2: Completion of project planning phase

0 days

Mon 12/17/18

Mon 12/17/18

66

sponsors

$0.00

3

Development phase

54 days

Tue 12/18/18

Fri 3/1/19

$20,480.00

3.1

Green building Technology concept implementation

10 days

Tue 12/18/18

Mon 12/31/18

67

operation manager

$3,600.00

3.2

Technology simulation

12 days

Tue 1/1/19

Wed 1/16/19

69

technical team

$3,072.00

3.3

Originating requirements implementation

6 days

Thu 1/17/19

Thu 1/24/19

70

business analyst

$2,304.00

3.4

Functional requirements implementation

6 days

Thu 1/17/19

Thu 1/24/19

70

technical head

$2,160.00

3.5

Performance requirements implementation

4 days

Fri 1/25/19

Wed 1/30/19

71,72

operation manager

$1,440.00

3.6

Derived requirements implementation

4 days

Thu 1/31/19

Tue 2/5/19

73

technical team

$1,024.00

3.7

Energy trends implementation

4 days

Wed 2/6/19

Mon 2/11/19

74

business analyst

$1,536.00

3.8

Trade off analysis

4 days

Tue 2/12/19

Fri 2/15/19

75

interior designer

$1,600.00

3.9

Technology renew

4 days

Mon 2/18/19

Thu 2/21/19

76

project manager

$1,760.00

3.10

Catering service contract

4 days

Fri 2/22/19

Wed 2/27/19

77

finance manager

$1,280.00

3.11

Electricity contract

1 day

Thu 2/28/19

Thu 2/28/19

78

interior designer

$400.00

3.12

Other strategic planning

1 day

Fri 3/1/19

Fri 3/1/19

79

caterers

$304.00

3.13

Milestone 3: Completion of project development phase

0 days

Fri 3/1/19

Fri 3/1/19

80

HR manager

$0.00

4

Project control and monitoring phase

11 days

Mon 3/4/19

Mon 3/18/19

$4,608.00

4.1

Building inventory

1 day

Mon 3/4/19

Mon 3/4/19

81

technical head

$360.00

4.2

Developing training programs

1 day

Tue 3/5/19

Tue 3/5/19

83

operation manager

$360.00

4.3

Energy consumption ideas

1 day

Wed 3/6/19

Wed 3/6/19

84

technical team

$256.00

4.4

Energy consumption strategies

1 day

Wed 3/6/19

Wed 3/6/19

84

business analyst

$384.00

4.5

Cost analysis based on Green building

1 day

Thu 3/7/19

Thu 3/7/19

85,86

interior designer

$400.00

4.6

Energy profile per square foot

1 day

Fri 3/8/19

Fri 3/8/19

87

interior designer

$400.00

4.7

Green technology strategic approach

1 day

Mon 3/11/19

Mon 3/11/19

88

HR manager

$240.00

4.8

Green technology tactical approach

1 day

Tue 3/12/19

Tue 3/12/19

89

technical head, technical team

$616.00

4.9

Surveillance camera setting

1 day

Wed 3/13/19

Wed 3/13/19

90

technical head, technical team

$616.00

4.10

Accommodation development for 80 staffs for OPAIC building

1 day

Thu 3/14/19

Thu 3/14/19

91

technical head

$360.00

4.11

Space efficiency analysis

1 day

Fri 3/15/19

Fri 3/15/19

92

operation manager

$360.00

4.12

ROI analysis

1 day

Mon 3/18/19

Mon 3/18/19

93

technical team

$256.00

4.13

Milestone 4: Completion of project monitoring and control phase

0 days

Mon 3/18/19

Mon 3/18/19

94

business analyst

$0.00

5

Project closure phase

9 days

Tue 3/19/19

Fri 3/29/19

$3,640.00

5.1

Operation testing

1 day

Tue 3/19/19

Tue 3/19/19

95

operation manager

$360.00

5.2

Stocking

1 day

Wed 3/20/19

Wed 3/20/19

97

technical team

$256.00

5.3

Project flow and timing details

1 day

Thu 3/21/19

Thu 3/21/19

98

business analyst

$384.00

5.4

Resupply scheduling

1 day

Thu 3/21/19

Thu 3/21/19

98

interior designer

$400.00

5.5

Grand opening planning for the business

1 day

Fri 3/22/19

Fri 3/22/19

99,100

sponsors

$520.00

5.6

Verification

1 day

Mon 3/25/19

Mon 3/25/19

101

technical head

$360.00

5.7

Validation

1 day

Tue 3/26/19

Tue 3/26/19

102

operation manager

$360.00

5.8

Post project maintenance plan

1 day

Wed 3/27/19

Wed 3/27/19

103

technical team

$256.00

5.9

Project approval requirements

1 day

Thu 3/28/19

Thu 3/28/19

104

business analyst

$384.00

5.10

Project approval documentation

1 day

Fri 3/29/19

Fri 3/29/19

105

technical head

$360.00

5.11

Milestone 5: Completion of project closure phase

0 days

Fri 3/29/19

Fri 3/29/19

106

operation manager

$0.00

Maori Protocol

The Maori perspectives or Maori protocol is being used in every business organizations for minimizing the risk factors and make easy decisions for the commercial success of the company. For organizational change management this protocol is used by the project owners. For example in this additional garden and BBQ area development in OPAIC building roof, the project authority should have considered the concept of Maori Protocol. Ng? Kaihaut? Tikanga Taiao has developed this protocol for the business change management. For the wellbeing of the present and future generation, by ensuring the culture, spiritual health this protocol is necessary to be followed by the project associates. The principle followed by the protocol defines the following:

  • Principle of partnership
  • Protection principle
  • Participation principle
  • Potential and productive relationships
  • Informed decision making principle
  • 6. Change management plan

The change management program developed for the project is followed by the below phases:

  • Proper identification of changes
  • Building technical team for green building
  • Creating project change vision
  • Removal of different obstacles
  • Integrate changes
  • Implementation of changes

In order to obtain life changing opportunities and long term sustainability it is necessary for the company to consider different aspects of change management protocols and the above mentioned steps should be followed by the project managers and team members respectively. The EPA will try to make sure that the Maori have accurate access to the decision making approach. Though, in this approach the new issues outside the actual submission can never be raised.

7. Communication management plan

It is necessary for the project manager and the project team members to communicate with each other following all the communication details. In order to design an additional garden area for the staffs to arrange summer programs it is necessary to communicate with the rest of the project team members to make them more familiar about the project requirements and the success criteria as well. It has been expected that if the project assumptions are framed based on the BBQ project success criteria then the final interior or the ultimate garden design area will be come up as a successful one. However, professional communication is a very important thing that has to be followed by each of the project team members during the initiation, planning and project development period. The factors considered for the communication are purpose, weekly status report, target audience, frequency, owner of the communication and distribution channel. The communication plan developed for this specific project is elaborated below:

ID

Communication
Vehicle

Target
Audience

Description/Purpose

Frequency

Owner

Distribution
Vehicle

Internal /
External

Comments

1

Weekly status report

Project Team

Communicate updated project status

Monthly

John Lee

email and presentation

Both Internal & External

The project status report will help to monitor the progress of the project

2

Weekly progress report

project development team members

to develop the project objectives

weekly

Steve smith

email and presentation

Internal

It will help to design the project success criteria

3

Weekly status report

project manager and sponsors

To estimate the total time and budget

Monthly

Steve smith

email and presentation

Internal and external

To meet the expectation of the consumers

4

Weekly progress details report

Interior designer and project planner

To discuss about the details of BBQ area interior

Monthly

Andrew Jackson

Presentation and conference

Internal and external

To develop a eye soothing and attractive design and environment to catch more customers

 5

Weekly progress details report

project planner and manager

discuss about catering and accommodation

weekly

Steve smith

email and presentation

Internal and external

It will help to create a proper accommodation for the customers who are attending the program

 6

Weekly progress details report

technical department

About the application of green building principles

Monthly

William Watson

face to face meeting and presentation

Internal and external

It will make sure the energy will be consumed

7

Feasibility report

finance team and sponsors

Total budget and time

weekly

Rodric Fleming

face to face meeting

Internal and external

To successfully complete the project within estimated budget and time.

8. Cost baseline and procurement plans

Creation of project budget, cost baseline and a project plan is essential for managing this project and accomplish this within estimated time as well. Cost baseline establishes proper balance between cost and time. Mainly for the interior the cost may vary with changing timeline. However proper cost baseline will help to at-least estimate the expected time to complete a specific activity.

The project management plan for “Addition of a garden and BBQ area on the roof of the OPAIC building”, five parent phases are applied in terms of project initiation, planning, development, monitor and controlling and closure. Though, at the closure phase the project does not actually complete rather a project needs post project maintenance also for giving satisfactory resultant to the customers.

9. Quality baseline and management plan

The mission of the “Addition of a garden and BBQ area on the roof of the OPAIC building” project is to serve quality food and beverages to the staffs who is attending the functions. They must have a unique selling point for the fusion barbeque cuisine and also social perspectives related to the concept that may separate the food quality from other restaurants and caterers. The prices for the food products are needed to be reasonable enough so that more number of clients can afford them.

Items

Targets

Food products

Affordable

Tasty and delicious

Beverages

Affordable

Unique than others

Accommodation

Comfortable

Well decorated

For other tasks the quality descriptions are mentioned below:

Task Name

Quality

schedule for Addition of garden and BBQ area

 

Understanding project details

High

Developing project SMART goal

High

Site analysis of OPAIC building

High

Creating project assumptions

High

Identifying project milestone

High

Describing project purpose to the project sponsors

High

Requirements gathering

High

Requirements specifications

Medium

Requirements analysis

Medium

Project assumptions and triple project constraints

High

Summary milestones

High

Project risks and risk register

High

Budget summary

High

Project stakeholders and resource management details

High

High level functional and non-functional project requirements

High

Project description and boundaries

High

Project assumptions and triple project constraints

High

Summary milestones identification

High

Feasibility analysis

High

Interview for the project team

Medium

Project team development

Medium

Details market research

Medium

Acquisition of project vendors

Medium

Probability plan for consumer base

Medium

Interior design planning

High

Exterior design planning

High

Site proposal for OPAIC plan

High

Food menu planning

High

OPAIC building area/location acquisition

High

Permit for the business registry

High

Kitchen equipments

High

Renovation materials adoption

High

BBQ area demolition

High

Garden and BBQ area construction

High

Repairing and construction faults

High

Installation of equipments

High

Janitorial requirements analysis

Medium

Onsite freezers

Medium

Radio and television

Medium

News papers and telephone calls

Medium

Posters and banners

Medium

Personnel acquisition

Medium

Employee on job training classes

Medium

Workshop arrangements

Medium

Adopting training materials

Medium

Work schedule development

Medium

Janitorial staffing for the project

Medium

Risk management plan

Medium

Contingency planning

Medium

Communication program development

Medium

Budget and time management plan

Medium

Change management plan

Medium

Technology implementation planning

Medium

Incorporating green building principles

Medium

Green building Technology concept implementation

High

Technology simulation

High

Originating requirements implementation

High

Functional requirements implementation

High

Performance requirements implementation

High

Derived requirements implementation

High

Energy trends implementation

High

Trade off analysis

High

Technology renew

High

Catering service contract

Medium

Electricity contract

Medium

Other strategic planning

Medium

Building inventory

Medium

Developing training programs

Medium

Energy consumption ideas

Medium

Energy consumption strategies

Medium

Cost analysis based on Green building

High

Energy profile per square foot

High

Green technology strategic approach

High

Green technology tactical approach

High

Surveillance camera setting

High

Accommodation development for 80 staffs for OPAIC building

High

Space efficiency analysis

High

ROI analysis

High

Operation testing

High

Stocking

High

Project flow and timing details

High

The fragrance and essence of the food products they will be serving should be absolutely unique. Besides the food products the quality of accommodations for the additional garden and BBQ area on the roof of the OPAIC building should be comfortable for the staffs who will be attending the programs and functions arranged. The more delicious foods they will serve on time and good quality that much clients they can grab. For promoting the “Addition of a garden and BBQ area on the roof of the OPAIC building” project online social media platform will also be used. Moreover, the main three components that are necessary to measure include price, quantity and quality of foods and beverages.

10. Risk management plan with a risk register

For “Addition of a garden and BBQ area on the roof of the OPAIC building” project risk management act as a leadership approach which make sure that the potential threats that may interrupt the project success will be identified and dealt by the project manager and other team members before the derail of the project. Risk management is a key process used by the project managers to monitor and control the project. With the help of a risk log the project manager can develop project plans eventually and successfully. Easily project managers can spot the troubles and can also make easy decisions.

Not only can this but also fundamental business level changes also be incorporated to the project with proper risk management strategies. Where the projects need enough focus and concentration from the team members are defined by the identification of proper risks. Vast and robust enterprise level risk management approaches are required to be developed by the project team members to mitigate the different project level issues that the “Addition of a garden and BBQ area on the roof of the OPAIC building” project may face during the development and implementation phase. The risk register developed for this specific project is elaborated below:

Risks

Impact

Frequency

Mitigation strategies

Lack of technical experts

High

Rare

On job technical training classes and workshops are to be arranged by the project owners to make the project team members familiar with the project objectives. Not only this, but also for developing green buildings at the initiation team members hiring phase their skills and performance details should be measured.

Incorrect budget plan

High

Possible

Before the development of the project the owner should calculate the project budget to make sure that the project will be profitable for them. However, the sponsors should also invest the equal amount of financial support for the development of the project.

Incorrect resource assignment

Medium

Frequent

For each and individual project activity proper resources should be allocated by the project head based on their skills and knowledge. They should have proper engagement to their job roles to satisfactorily complete their responsibilities within the estimated time and budget.

Inaccurate time management

High

Possible

Improper management of time will negatively affect the overall budget or cost and scope of the project too. Thus, at the project initiation phase, proper time based on the project complexity should be prepared to avoid additional cost oriented issues.

11. Project approval requirements

The project sponsors and the project manager’s role are to approve the “Addition of a garden and BBQ area on the roof of the OPAIC building” project within estimated budget and time. The project requirements are dependent on the project charter elements. The necessary high level project approval requirements are as follows:

  • Project purpose or details project justification
  • SMART project objectives and relevant success criteria
  • High level functional and non-functional project requirements
  • Project description and boundaries
  • Project assumptions and triple project constraints
  • Summary milestones
  • Project risks and risk register
  • Budget summary
  • Project stakeholders and resource management details
  • Project signoff documents
  • Assigned managers and authority level responsibilities and sponsors details
  • Final documentation for “Addition of a garden and BBQ area on the roof of the OPAIC building” project

References

Ahern, T., Leavy, B., & Byrne, P. J. (2014). Complex project management as complex problem solving: A distributed knowledge management perspective. International Journal of Project Management, 32(8), 1371-1381.

Boud, D., Cohen, R., & Sampson, J. (Eds.). (2014). Peer learning in higher education: Learning from and with each other. Routledge.

Braglia, M., & Frosolini, M. (2014). An integrated approach to implement project management information systems within the extended enterprise.International Journal of Project Management, 32(1), 18-29.

Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Dhaugoda, S., & Dang, J. (2015). ''Asian BBQ House''restaurant business plan.

Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC Press, LLC.

Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational excellence. pearson.

Heikkila, M., Bouwman, H., Heikkilä, J., Haaker, T., Lopez-Nicolas, C., & Riedl, A. (2016). Business Model Innovation Paths and Tools. In Bled eConference (p. 6).

Heldman, K. (2015). PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.

Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity. International Journal of Project Management, 33(2), 291-298.

Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), 1377-1392.

Kami, N. (2015). U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark Office.

Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing your project. AMACOM Div American Mgmt Assn.

Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014). Project risk management methodology for small firms. International Journal of Project Management, 32(2), 327-340.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), 202-217.

Pemsel, S., & Wiewiora, A. (2013). Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42.

Sanchez, M. A. (2015). Integrating sustainability issues into project management. Journal of Cleaner Production, 96, 319-330.

Spundak, M. (2014). Mixed agile/traditional project management methodology–reality or illusion?. Procedia-Social and Behavioral Sciences, 119, 939-948.

Todorovic, M. L., Petrovi?, D. ?., Mihic, M. M., Obradovic, V. L., & Bushuyev, S. D. (2015). Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), 772-783.

Turner, R. (2016). Gower handbook of project management. Routledge.

Verzuh, E. (2015). The fast forward MBA in project management. John Wiley & Sons.

Walker, A. (2015). Project management in construction. John Wiley & Son.


Buy AM804001 The Roles and Importance of Project Management Answers Online

Talk to our expert to get the help with AM804001 The Roles and Importance of Project Management Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for AM804001 The Roles and Importance of Project Management Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.