Case Study Project Management For Data Warehouse Development Project

Discuss about the case study Project Management for Data Warehouse Development Project.

Answer:

Project Integration Management

Project Charter

The project deals with developing and establishing a multidimensional, multilevel data warehouse on Microsoft 2012 SQL Server Platform. The project will also ensure the security of the files in the warehouse along with the validation of the data stored. Furthermore, the reviewing of the errors in ETL processes and training of the staffs for using the warehouse also include within the project deliverables.

Project Title

Establishing new data warehouse capability within the existing SST IT infrastructure

Project Location

Southern State TAFE

Brief Description of the Project

The project “Establishment of a new warehouse” aims to ensure the cross application production reporting capability. The undertaken project will encompass data warehouse provision, dashboard production and will provide reporting capability of the BI portal.

Prepared By

[Name of the Student]

Date

[Mention Date]

Version

1.0

Scope Statement

An efficient project scope statement in the project management plan allows in identifying the detailed scope of the undertaken project along with constraints required for the project. In this particular project, the scope is mainly based on enhancing the performance of the organization by brin


ging a large number of changes in the systems and frameworks. These are mainly targeted by using more efficient working database and warehouse systems and other technical changes.

Management of Project Scope, Execution & Control, Change Management

As there are many scopes in a project, management of each scope is needed. For this, the actual scopes of this project and the out of scope parts are to be determined.

Scope of the Project

Following are the in scope of the project.

  • To develop a multi-dimensional database of the warehouse based on Microsoft 2012 SQL Server Platform
  • To develop a SharePoint site for using the Business Intelligence Portal
  • To implement a data load and file transfer mechanism according to the SST infrastructure standards
  • To develop a security model for BI portal and data warehouse that provide a conjunction along with Active Directory Groups
  • To define the Key Performance Indicators (KPI) along with the Balance Score card
  • To create a link between the BI Portal and SST intranet
  • To train the SST staff for using the data warehouse and BI portal

Out of Scope

The following will be excluded in the project.

  • To link any other system with the data warehouse
  • To create the data extraction from any other systems

Project Execution and Control

The project will be executed according to the plan blueprint. The plan blueprint will be developed following the work breakdown structure as follows:

Figure: Work Breakdown Structure

(Source: Created by Author)

Change Management

Previously, an estimated task schedule was provided for the required project plan. However, after analysis with the actual project scenario and using latest technical equipments, several changes will be made in that table as follows:

Task Name

Duration

Data Warehouse Development and Installation Project

375 days

Project Initiation Phase

6 days

Understanding the Requirement

2 days

Conducting feasibility test

2 days

Developing the project charter

2 days

Project Planning Phase

39 days

Develop project plan

15 days

Create project scheduling

5 days

Create resource allocation

5 days

Developing communication plan

4 days

Forming the team

10 days

Execution phase

285 days

Development of Data Warehouse

103 days

Develop the architecture

30 days

Collect the data from various sources

5 days

Develop the multidimensional cube of the warehouse

20 days

Develop the blueprint of hardware system

10 days

Develop the system design of Business Intelligence Portal

23 days

Design the User Interface of the system

15 days

Implementation phase

87 days

Hardware implementation

20 days

Designing the database

20 days

Software implementation of the data warehouse system

15 days

Development of the SharePoint site

10 days

Connecting the Business Intelligence Portal and data warehouse

15 days

Connecting the warehouse with another system

7 days

Deployment and Testing Phase

95 days

testing the architecture design

15 days

software testing

20 days

data validation testing

10 days

security testing

15 days

unit testing

5 days

Risk identification and mitigation

30 days

closing phase

45 days

creating the link to BI portal and SST intranet

10 days

training of the staffs

20 days

maintenance of the warehouse

15 days

[The ones marked in yellow have been changed]

Management of changes will be needed as some of the tasks will need lesser time due to use of technology instead of manual work and some will take greater time as more emphasis are to be put into the tasks.

Project Quality Management

Planning

This project will have a number of phases that must be conducted one after the order in order to complete all of them with success. The order and type of tasks will be as follows:

Task No

Task Name

1

Data Warehouse Development and Installation Project

1.1

Project Initiation Phase

1.1.1

Understanding the Requirement

1.1.2

Conducting feasibility test

1.1.3

Developing the project charter

1.2

Project Planning Phase

1.2.1

Develop project plan

1.2.2

Create project scheduling

1.2.3

Create resource allocation

1.2.4

Developing communication plan

1.2.5

Forming the team

1.3

Execution phase

1.3.1

Development of Data Warehouse

1.3.1.1

Develop the architecture

1.3.1.2

Collect the data from various sources

1.3.1.3

Develop the multidimensional cube of the warehouse

1.3.1.4

Develop the blueprint of hardware system

1.3.1.5

Develop the system design of Business Intelligence Portal

1.3.1.6

Design the User Interface of the system

1.3.2

Implementation phase

1.3.2.1

Hardware implementation

1.3.2.2

Designing the database

1.3.2.3

Software implementation of the data warehouse system

1.3.2.4

Development of the SharePoint site

1.3.2.5

Connecting the Business Intelligence Portal and data warehouse

1.3.2.6

Connecting the warehouse with another system

1.3.3

Deployment and Testing Phase

1.3.3.1

Testing the architecture design

1.3.3.2

Software testing

1.3.3.3

Data validation testing

1.3.3.4

Security testing

1.3.3.5

Unit testing

1.3.3.6

Risk identification and mitigation

1.4

closing phase

1.4.1

Creating a link to BI portal and SST intranet

1.4.2

Training of the staffs

1.4.3

Maintenance of the warehouse

Control

The project will be controlled as per the planning made for the scheduling. Each of the tasks will be done one after another to execute the project effectively.

Configuration Management

The systems will be configured according to the requirements once the project starts. Latest technical configurations and best possible equipments will be used for the project.

Human Resource Management

HR Planning

For this project, HR planning is necessary for recruitment of the stakeholders that are not available inside the organization. The following will be the duties of the HR team in this project.

HR Department

Duty

Examination Team

To test the stakeholder candidates for possible selection

Recruitment Team

To recruit candidates according to the test results and recruitment guidelines

Management Team

To manage the employees and delegate the tasks in the project

Program Handling Team

To handle the project according to plan

Resource Management Team

To manage allocated resources according to the requirements of the project

Employee Concern Team

To manage and address concerns of the employees

Procurement Team

To procure necessary resources after allocation

Organisational Chart/s

Role of the Project Manager and Project Team

The role of a project manager is huge. He has the duty of managing the whole project in the right direction. In this project, the role of the project manager will be the following:

Managing the Project – The project manager will manage the project according to the requirements. After analysis of all the requirements, the research team will send a report to the project manager. He will analyse this report and financial statement and will decide the direction of the project.

Resource Allocation – After analysing the project requirements, the manager will analyse financial statement and available resources. He will then allocate resources in each field of the project.

Employee Management – The project manager will delegate tasks to the employees according to their specializations. He has to ensure that every employee completes their jobs effectively and efficiently.

Analysis of Project Reports – The project manager will analyse the regular project reports sent to him to judge the progress of the project. He will then decide the future and the direction of the project.

The project team is responsible for conducting the project according to requirements. The following are the duties of the project team.

Project Operations – The project team will be responsible for conducting the project according to the requirements. The team has to ensure that all the operations are being conducted according to the project plan.

Resource Management – The project team will manage resources allocated to them according to the requirements. They have to ensure the resources are spent in such a way that no extra expenses are encountered during the project.

Preparation and Sending of Project Reports – The project team should prepare and send regular project reports to the manager so that he is able to track the progress of the project.

Resources

The estimated resources for this project are as follows:

Task

Resource

Estimated Cost

Feasibility Test

Testing Softwares, Automated Analysis Tools

$1000

Employee/Expert Recruitment

Specialized Experts

$15000

Architecture Development

Architecture Softwares, Latest Computer Systems

$5000 + $20000

Data Collection

Internet Tools

$1000

Development of Blueprint, Intelligence Portal, User Interface

Design Softwares

$10000

Implementation of Architecture, Hardware, Blueprints, Designs

Technically Upgraded Systems

$10000

Testing (Software, Unit, Design, Security)

Testing Softwares

$2000

Staff Training

Specialized Trainers

$10000

Project Communications Management

Communications Plan

The following communication plan may be followed.

Vehicle

Description
Purpose

Frequency

Owner / Stakeholder

Internal/
External

Comments/
Distribution List

Project Report, Financial Report

The sponsors will check the reports and will decide on future investment.

Quarterly

Project Sponsors

External

Future Investment Policy

Future Service Details

Future service details will encourage more customers to come to the organization.

Weekly

Customers

External

Use of Service, Feedback

Project Report

Project Manager will decide the direction of the project based on the project report.

Weekly / Biweekly

Project Manager

Internal

Leading and managing of the project, project guidelines

Project Progress Report

Internal customers will understand the upgraded services.

Monthly

Internal Customer

Internal

Feedback

Tests Schedule

They will prepare the systems and make backups for the existing systems.

Daily

SST Staffs

Internal

System Quality Report

Test Results

They will further enhance the codes and designs.

Daily

Tester, Developers, Coder

Internal

Quality Report

Trainee Progress Report

Training team provides efficient training to the employees and staffs for using the data warehouse for storing and retrieving files.

Daily

Training Team

Internal

Updated Progress Reports

Financial and Protection Statements

Insurance company will be providing effort in regulatory and licensing business and data protection act.

Monthly

Insurance Company

External

Funds Reports

Security Information and Threat Reports

They will be responsible for maintaining the security of data both from internal and external parties.

Daily

Security Team

Internal

Security Reports

Data Reports

They are responsible for maintaining and administrating the data, and authentication the users

Biweekly

SST Administrator

Internal

Authentication Reports

Suitable Medium/s & Channels

The communication media according to stakeholders are as follows:

Stakeholder

Communication Medium

Project Sponsors

Phone calls, formal mails, fax

Customers

Advertisements

Project Manager

Face-to-face, phone calls, formal mails

Internal Customer

Leaflets

SST Staffs

Face-to-face

Tester, Developers, Coder

Face-to-face

Training Team

Face-to-face (Interactive)

Insurance Company

Mails, fax

Security Team

Face-to-face

SST Administrator

Mails, chats

Project Procurement Management 400

Processes to Support Project Procurement Background

In this particular project, procurement is necessary for assimilating all the necessary resources and using them effectively to proceed with the project according to the plan. Procurement will be necessary for technical equipments and employees / personnel.

Scope

Procurement of resources (technical or human) will help the company in the upgradation as well as expansion.

Contract Commencement Date

The contracts will commence from the start of the project (at least few days prior to the start of actual operations.

Number of Contractors

The number of contractors will depend on the decision of the company on the ground of outsourcing. However, the number should not exceed a limit such that the company is forced to overspend in the project.

Contract Terms

The contract terms should favour both the contractor and the company. The contractor should be to benefit from the terms and the company should not overspend due to the terms.

Funding

The company should provide sufficient funding. But the company must not overspend.

Estimated Contract Value

The estimated total contract value is $100,000.

General Conditions

The general conditions will be following:

  • The contractor should not break the terms of the contract unless mutually agreed.
  • The company holds the right to terminate any contract anytime.
  • The contractor will not be responsible for any effect of the fault from the company’s part.
Approval to Proceed

The final approval for proceeding will be given by the project manager.

Outsourcing

In this project, there are several tasks that cannot be done by the internal employees of the organization only. Hence, outsourcing is needed in order to hire outsiders in this project. A simple outsourcing plan has been provided as below.

Project Task

Outsourcing Plan

Valuation of Assets

Hiring of Insurance Company

Employee Training

Hiring of external and expert trainers

System Security Checks (Advanced Level)

Use of external security experts

Marketing and Promotion

Use of an advertisement agency

Planning Purchases and Acquisitions

A purchase plan for the company along with estimated budget is provided below.

Asset / Requirement

Estimated Budget

Updated Hardware Systems

$100,000

Latest Versions of Softwares

$50,000

System Equipments

$20,000

Others

$25,000

Bibliography

Calderón, A. and Ruiz, M., 2014. Bringing Real-life Practice in Software Project Management Training Through a Simulation-based Serious Game. InCSEDU (2) (pp. 117-124).

Hughes, R., 2012. Agile Data Warehousing Project Management: Business Intelligence Systems Using Scrum. Newnes.

Kerzner, H.R., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L.P., 2014. Critical chain project management. Artech House.

Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.

Menzies, T., Brady, A., Keung, J., Hihn, J., Williams, S., El-Rawas, O., Green, P. and Boehm, B., 2013. Learning project management decisions: a case study with case-based reasoning versus data farming. IEEE Transactions on Software Engineering, 39(12), pp.1698-1713.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success.International Journal of Project Management, 32(2), pp.202-217.

Nagarajan, R., Joseph, A.V. and Sujatha, S., 2015. Behavioural Aspects of Software Project Management-In-House Software Development. Indian Journal of Science and Technology, 8(S3), pp.1-9.

O’Connor, R.V. and Laporte, C.Y., 2012, June. Software project management in very small entities with ISO/IEC 29110. In European Conference on Software Process Improvement (pp. 330-341). Springer Berlin Heidelberg.

Reiss, G., 2013. Project management demystified: Today's tools and techniques. Routledge.

Ryerson, M.S. and Woodburn, A., 2016. Manage Flight Demand or Build Airport Capacity?. ACCESS Magazine, 1(48).

Sen, A., Ramamurthy, K. and Sinha, A.P., 2012. A model of data warehousing process maturity. IEEE Transactions on Software Engineering,38(2), pp.336-353.

Sun, Y. and Schonfeld, P., 2015. Stochastic capacity expansion models for airport facilities. Transportation Research Part B: Methodological, 80, pp.1-18.

Teller, J., Unger, B.N., Kock, A. and Gemünden, H.G., 2012. Formalization of project portfolio management: The moderating role of project portfolio complexity. International Journal of Project Management, 30(5), pp.596-607.

Trendowicz, A. and Jeffery, R., 2014. Software project effort estimation: Foundations and best practice guidelines for success. Springer.

Varajão, J., Dominguez, C., Ribeiro, P.M.G.D.A. and Paiva, A., 2014. Failures in software project management–are we alone? A comparison with construction industry. International journal of modern project management,2(1), pp.22-27.


Buy Case Study Project Management For Data Warehouse Development Project Answers Online

Talk to our expert to get the help with Case Study Project Management For Data Warehouse Development Project Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.

Get Online Support for Case Study Project Management For Data Warehouse Development Project Assignment Help Online

Copyright © 2009-2023 UrgentHomework.com, All right reserved.