Coit12208 The Resolving Resource Allocation Assessment Answers

The case study simulates a project management scenario where the student takes on the role of project manager. The case information is not complete so where necessary students will have to argue the pros and cons of any assumptions they make. If necessary, students are expected to find relevant information in the academic literature to justify their answers and provide appropriate references.
The following information is provided to assist students to develop their assessment solution:
Product development case description
Specific assessment questions that must be answered
Information regarding the submission of the assessment
Marking guide

Important notes regarding assignment submission
1. You must aim to submit your assignment at least 1 hour before the due date. This will avoid unnecessary late penalties if you have any technical issues while submitting your assignment.
2. If you do have a problem uploading your assignment online and cannot get help from TASAC, make sure that you email your assignment files to your tutor before the due date.This will allow your tutor to view the work that was completed before the deadline. Note that you will also be required to submit the assignment online through Moodle.
3. Any drafts in Moodle may be automatically submitted by Moodle at the due date. However,you must not rely on this for your submission. Note that this does mean that you should not leave something uploaded as a draft if you do not want it to be submitted automatically. If you upload after the due date (this includes students with extensions) you must ensure that you press submit for marking or you may incur a further late penalty.

Preparation for the assignment
1. You must complete the MP practicals 1 and 2 before you start this assignment.
2. You must also complete practical 3 before you attempt to add resources to your assignment.
You are required to take your Microsoft Project practical’s and this assignment to your tutorial/practical classes from week 3 onwards. The course is scheduled to commence the practical’s in week 3 and you are expected to start work on this assignment in week 6 (or earlier).

Answer:

a) Explanation about resolving resource allocation

Over allocation problem is present in the project and it can be resolved by resource levelling. It is identified that while resources of the project are levelled, the activities that are associated with this project are not disjointed and therefore adjustment is not reflected on the separate assignment on the tasks. It is analysed that for levelling the project resources, the duration of the project is increases but the cost that is associated with this project are remains the same.

b) Comparison

WHA_PartAQ1.mpp

WHA_PartAQ2.mpp

Total duration

Total cost

Total duration

Total cost

177 days

$657,120.00

301days

$657,120.00

c) Difference between the mpp files

 It is found that in Part AQ1mpp, the time that is generally needed for completing the project is around 177 days whereas in PartAQ2, it is reflected that the time that is generally required for completing the project is around 301days. The change in the duration of the project is generally because of levelling the resources of the project that are generally overallocated.

d) Problems in Ms project after levelling of resources

It is found that after levelling the resources of the project, there is no change in the sequence of the tasks however the duration of the project generally changes after the resources of the project are levelled.

Part A question 3

Memo

To: Harold Steptoe

From: << Student name >>, Project Manager

Date: 13-09-18

Sub: Providing details about the planning stage completion.

Message

 The planning phase of the project is properly deliberate and it is identified that the whole project will be completed successfully within the time-period of 301 days by presumptuous that the whole project will usually started on 1st October 2018. It is found that the project will be completed by 23rd December 2019. It is found that the duration of the project generally enhances due to levelling of project resources which are mainly related with the project. The duration of the project can be reduced by hiring a more number of people so that the project activities can be accomplished successfully within a small period of time. In addition to this, the projected cost for each of the resource of the project is provided in the below table:

Resource Name

Cost

Craft Artisan (CA)

$ 95.00/hr

Business Analyst (BA)

$ 120.00/hr

Knowledge Analysis (KA)

$ 110.00/hr

Software engineers (SE)

$ 110.00/hr

Network engineers (NE)

$ 110.00/hr

Mechanical Engineer (ME)

$ 100.00/hr

Workshop Assistant (WA)

$ 50.00/hr

Accommodation

$ 100.00

Flight

$ 200.00

The project schedule is provided below:

Part A question 4

Explanation for the resource choice

 It is found that software engineer must be added for reducing the duration of the project.

Comparison

WHA_PartAQ3.mpp

WHA_PartAQ4.mpp

Total duration

Total cost

Total duration

Total cost

286.5 days

$657,120.00

301 days

$657,120.00

Explanation

It is found that we have shortened “system population” of both purchase order and human resource in order to decrease the time period of the project. It is found that the entire time period of the project reduced to 286.5 days after levelling the overallocated resources. The differences in both PartAQ3 and PartAQ4 due to overcoming the project resources.

Part A question 5 

a) Project risks

Quality issues

Impact

Probability

Degree

 Improper analysis of project quality

Due to improper analysis of project, the quality of the project gets affected.

High

High

Inappropriate platform configuration

Due to improper configuration of the project, the project quality can get affected

High

High

b) Incorporating activities in WBS

WBS number

Task Name

Duration

Resource

5.2.2

 After platform configuration testing needs to be dine for ensuring that configuration is done properly

 2 days

Software engineer

Part A question 6

The tasks that are left out of the project will generally help in making the project include:

  • Training of team members and
  • Project Review

Change

Impact on Project duration

Explanation

 Sprint 1

 Longer

 Sprint 1 started at the same time as the as the Leichardt Workshop

Sprint 2

Longer

Sprint 2 finish at the same time when the completion of testing of the HRM

Sprint 3

Shorter

It started at once Hardware contracts are awarded.

Sprint 4

Shorter

It started after the testing phase gets completed.

Change

Impact on Project Cost

Explanation

Sprint 1

Greater

 This is because of adding new resources KE, WA.

Sprint 2

Greater

This is due to adding new resources WA, CA and BA.

Sprint 3

Greater

This is due to adding new resources like KE and WA

Sprint 4

Lesser

This is due to reduction in the duration in completing the activity from 3 weeks to 2 weeks.

Bibliography

Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and project success in different project governance contexts. International Journal of Project Management, 33(6), pp.1377-1392.

Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of Cleaner Production, 96, pp.319-330.

Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature review with a critical look at the brave new world. International Journal of Project Management, 33(2), pp.278-290.

Todorovi?, M.L., Petrovi?, D.?., Mihi?, M.M., Obradovi?, V.L. and Bushuyev, S.D., 2015. Project success analysis framework: A knowledge-based approach in project management. International Journal of Project Management, 33(4), pp.772-783.


Buy Coit12208 The Resolving Resource Allocation Assessment Answers Online


Talk to our expert to get the help with Coit12208 The Resolving Resource Allocation Assessment Answers to complete your assessment on time and boost your grades now

The main aim/motive of the management assignment help services is to get connect with a greater number of students, and effectively help, and support them in getting completing their assignments the students also get find this a wonderful opportunity where they could effectively learn more about their topics, as the experts also have the best team members with them in which all the members effectively support each other to get complete their diploma assignments. They complete the assessments of the students in an appropriate manner and deliver them back to the students before the due date of the assignment so that the students could timely submit this, and can score higher marks. The experts of the assignment help services at urgenthomework.com are so much skilled, capable, talented, and experienced in their field of programming homework help writing assignments, so, for this, they can effectively write the best economics assignment help services.


Get Online Support for Coit12208 The Resolving Resource Allocation Assessment Answers Assignment Help Online


Copyright © 2009-2023 UrgentHomework.com, All right reserved.